12653 N NORRIS AVE 91342
Certificate Information: 12653 N NORRIS AVE 91342
- Application / Permit
- 20014-20000-02162
- Plan Check / Job No.
- B20VN07018
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (12'-0" x 14'-0") TO AND CONVERT (E) (18'-0" x 18'-0") DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 9/28/2020
- Issuing Office
- Current Status
- CofO Issued on 3/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2020 | DAWN MC NULTY |
| Corrections Issued | 6/3/2020 | DAWN MC NULTY |
| Building Plans Picked Up | 6/4/2020 | APPLICANT |
| Applicant returned to address corrections | 7/28/2020 | ROSENDO MEDINA |
| Plan Check Approved | 9/28/2020 | TROY DEGUZMAN |
| Issued | 9/28/2020 | APPLICANT |
| CofO in Progress | 4/20/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 3/24/2023 | DANIEL ORRANTE |
| CofO Issued | 3/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 6/24/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/25/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | GABRIEL ROBLES |
| ZI | Cleared | 9/15/2020 | KORA MCNAUGHTON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/1/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 10/1/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 10/5/2020 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/15/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/15/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/23/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 10/23/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/28/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/28/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/9/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 11/9/2020 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 11/9/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/12/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/12/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/12/2020 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/17/2020 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/23/2020 | Approved | JENNIFER RABUCHIN |
| Final | 1/27/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/27/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2021 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 1/27/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 2/10/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 2/10/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/10/2021 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 2/10/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 2/18/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/18/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 2/18/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/19/2021 | Approved | JENNIFER RABUCHIN |
| Final | 4/19/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 4/19/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/19/2021 | Approved | JENNIFER RABUCHIN |