8928 N SUNLAND BLVD 91352
Certificate Information: 8928 N SUNLAND BLVD 91352
- Application / Permit
- 20014-20000-02159
- Plan Check / Job No.
- B20VN07011
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Charter School - middle
- Work Description
- CHANGE OF USE FROM (E) 119'5" X 174'8" (20,857 SQ.FT. ) OFFICE TO CHARTER SCHOOL FOR MIDDLE SCHOOL , REINFORCE CEILING FRAMING AT 1ST FLOOR, FIBER WRAP REINFORCEMENT THROUGHOUT , NFPA-13 FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 12/24/2020
- Issuing Office
- Current Status
- CofO Issued on 7/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 6/5/2020 | APPLICANT |
| Green Plans Picked Up | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | RARES BODEA |
| Corrections Issued | 6/30/2020 | RARES BODEA |
| Quality Review Completed | 7/13/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/13/2020 | APPLICANT |
| Applicant returned to address corrections | 10/16/2020 | RARES BODEA |
| Plan Check Approved | 12/24/2020 | RARES BODEA |
| Issued | 12/24/2020 | APPLICANT |
| TCO Issued (Expire Date: 02-08-2022) | 8/12/2021 | JEFFREY DURAN |
| TCO Issued (Expire Date: 08-10-2022) | 2/11/2022 | RICKEY JACKSON |
| CofO in Progress | 6/23/2022 | ANDREW DORSO |
| Permit Finaled | 7/5/2022 | JEFFREY DURAN |
| CofO Issued | 7/5/2022 | JEFFREY DURAN |
| Permit Finaled | 7/5/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 8/20/2020 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 9/3/2020 | AARON COSTA |
| Highway dedication | Cleared | 9/9/2020 | MARKOS PEREZ-BRAN |
| Certificate of Compliance | Cleared | 9/15/2020 | MARC WOERSCHING |
| Comm Cor/Mini-Mall | Cleared | 9/21/2020 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 9/23/2020 | MATTHEW CRAIG |
| Grading Pre-Inspection | Cleared | 10/7/2020 | MANUEL TEJADA |
| Specific Plan | Cleared | 10/8/2020 | PEGGY MALONE-BROWN |
| ZI | Cleared | 10/8/2020 | PEGGY MALONE-BROWN |
| DAS Clearance | Cleared | 10/20/2020 | RARES BODEA |
| Low Impact Development | Cleared | 11/6/2020 | ANDRES COVARRUBIAS |
| Fire Marshall Fire Life Safety | Cleared | 11/19/2020 | DOMINIQUE MEDINA |
Contact Information
| Contractor | Blackwell Development Inc; Lic. No.: 1070521-B | 13229 SEVENTH PLACE YUCAIPA, CA 92399 |
| Engineer | Baroonian,, Armen; Lic. No.: S4227 | 867 N FAIR OAKS AVE 100 PASADENA, CA 91103 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/30/2020 | Partial Approval | DAVID BURKHEAD |
| Pre-Inspection | 12/30/2020 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 1/26/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 2/1/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 2/2/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 2/2/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 2/3/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 2/4/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 2/4/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 2/5/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 2/5/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/8/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 2/8/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/10/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/11/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/12/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 2/17/2021 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/18/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/19/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/22/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/23/2021 | Approved | HAMID PISHEHVAR |
| Deputy Reinf. Concrete | 3/17/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 3/18/2021 | Conditional Approval | ANDREW DORSO |
| Light Gage Steel Frame | 3/22/2021 | Corrections Issued | ANDREW DORSO |
| Wall Anchors | 3/22/2021 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 4/6/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 4/12/2021 | Partial Approval | ROBERT DAVIS |
| Insulation | 4/16/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 4/26/2021 | Partial Inspection | ANDREW DORSO |
| Insulation | 5/6/2021 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 5/24/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/1/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 6/18/2021 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 6/22/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 6/29/2021 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 6/29/2021 | Partial Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 6/29/2021 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 6/29/2021 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 7/23/2021 | Conditional Approval | DANIEL VARNUM |
| Final | 7/28/2021 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Final | 7/28/2021 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 7/28/2021 | Approved | ANDREW DORSO |
| Reinforced Masonry Frame | 7/28/2021 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 7/28/2021 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 7/28/2021 | Not Ready for Inspection | ANDREW DORSO |
| Final | 7/30/2021 | OK for TCO | ANDREW DORSO |
| Green Building Final | 7/30/2021 | Approved | ANDREW DORSO |
| Smoke Detectors | 7/30/2021 | Approved | ANDREW DORSO |
| Deputy Drilled-In Anchors | 10/12/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 10/12/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 10/13/2021 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 10/14/2021 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 10/14/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 10/20/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Masonry | 10/20/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Masonry | 10/21/2021 | Conditional Approval | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 10/21/2021 | Partial Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 10/21/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 10/22/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 12/15/2021 | Conditional Approval | DANIEL VARNUM |
| Special/Order Compliance | 1/12/2022 | Partial Inspection | ANDREW DORSO |
| Final | 4/22/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 6/23/2022 | OK to Issue CofO | ANDREW DORSO |