7942 N LURLINE AVE 91306
Certificate Information: 7942 N LURLINE AVE 91306
- Application / Permit
- 20014-20000-02129
- Plan Check / Job No.
- B20VN06940
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 13' x 37' ADDITION OF 2 BEDROOMS AND BATHROOM. RELOCATE EX. BATHROOM. ALL WORK PER WFPP
- Permit Issued
- Issued on 8/11/2021
- Issuing Office
- Current Status
- CofO Issued on 3/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2020 | JEFFREY TANGONAN |
| Corrections Issued | 5/28/2020 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 8/18/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 8/6/2021 | JEFFREY TANGONAN |
| Building Plans Picked Up | 8/6/2021 | APPLICANT |
| Issued | 8/11/2021 | APPLICANT |
| CofO in Progress | 8/2/2023 | ALEXANDER HANDY |
| Permit Finaled | 3/22/2024 | JOHN JANSON |
| CofO Issued | 3/22/2024 | JOHN JANSON |
| Permit Finaled | 3/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/28/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/29/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 7/20/2021 | YVAINNE GALSIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2021 | Approved | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 9/27/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 9/27/2021 | Partial Inspection | HENRY KIM |
| Pre-Inspection | 9/27/2021 | Not Ready for Inspection | HENRY KIM |
| Footing/Foundation/Slab | 9/30/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 11/16/2021 | Partial Approval | STEVEN BACK |
| Green Building Rough | 11/16/2021 | Not Ready for Inspection | STEVEN BACK |
| Wood Frame | 11/16/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 11/23/2021 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2021 | Partial Approval | STEVEN BACK |
| Insulation | 11/24/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 2/15/2022 | No Access for Inspection | STEVEN BACK |
| Green Building Rough | 2/15/2022 | No Access for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 2/25/2022 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 4/22/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 4/22/2022 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 4/22/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 4/28/2022 | Approved | STEVEN BACK |
| Deputy Wood Construction | 5/10/2022 | Conditional Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 6/14/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 6/14/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Approved | STEVEN BACK |
| Green Building Rough | 6/14/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 6/14/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 7/25/2022 | Corrections Issued | STEVEN BACK |
| Insulation | 7/25/2022 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 9/7/2022 | Partial Approval | STEVEN BACK |
| Insulation | 9/7/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/6/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 10/6/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 10/11/2022 | No Access for Inspection | STEVEN BACK |
| Drywall Nailing | 11/3/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 7/10/2023 | Approved | DAVID SCANTLIN |
| Final | 7/10/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 7/10/2023 | Approved | DAVID SCANTLIN |
| HVAC-Final | 7/10/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 7/10/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 7/10/2023 | Approved | DAVID SCANTLIN |
| Final | 8/2/2023 | OK to Issue CofO | ALEXANDER HANDY |