10401-10403 N RUFFNER AVE 91344

Certificate Information: 10401-10403 N RUFFNER AVE 91344

Application / Permit
20014-20000-02116
Plan Check / Job No.
B20VN06915
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATT. (E) 2- CAR GARAGE, KITCHEN AND DINING ROOM INTO A (N) ACCESSORY DWELLING UNIT AND ADD A (N) BATHROOM FOR THE MASTER BEDROOM. WORK PER LA STD WFPP.
Permit Issued
Issued on 9/22/2020
Issuing Office
Current Status
CofO Issued on 10/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 TROY DEGUZMAN
Corrections Issued 6/3/2020 TROY DEGUZMAN
Building Plans Picked Up 6/4/2020 APPLICANT
Plan Check Approved 9/22/2020 YAQUB MIRZA
Issued 9/22/2020 APPLICANT
CofO in Progress 9/14/2021 MARK JOHNSON
CofO Issued 10/15/2021 MICHAEL SMITH
Permit Finaled 10/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/19/2020 JOHN TRIANTAFYLLOS
Address approval Cleared 8/19/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 8/19/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/20/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/20/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/9/2020 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 10/9/2020 Partial Approval MARK JOHNSON
Underground Mechanical 10/9/2020 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 10/15/2020 Partial Approval MARK JOHNSON
Excavation/Setback/Form/Re-Bar 10/15/2020 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 11/17/2020 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 11/17/2020 Approved MARK JOHNSON
Green Building Rough 11/17/2020 Not Ready for Inspection MARK JOHNSON
Rough-Elec/Plmb/HVAC 11/17/2020 Partial Approval MARK JOHNSON
HVAC-Rough 11/23/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/9/2020 Partial Inspection MARK JOHNSON
Green Building Rough 12/9/2020 Corrections Issued MARK JOHNSON
Interior/Exterior Lathing 12/9/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/15/2020 Approved MARK JOHNSON
Green Building Rough 12/15/2020 Approved MARK JOHNSON
Insulation 12/15/2020 Approved MARK JOHNSON
Rough-Elec/Plmb/HVAC 12/15/2020 Approved MARK JOHNSON
Shower Pan 12/15/2020 Approved MARK JOHNSON
Drywall Nailing 1/15/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 1/15/2021 Approved MARK JOHNSON
Sewer 5/7/2021 Approved MARK JOHNSON
Final 9/8/2021 Corrections Issued MARK JOHNSON
Green Building Final 9/8/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 9/8/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 9/8/2021 Not Ready for Inspection MARK JOHNSON
Final 9/14/2021 OK to Issue CofO MARK JOHNSON
Smoke Detectors 9/14/2021 Approved MARK JOHNSON