2361 W MOSS AVE 90065
Certificate Information: 2361 W MOSS AVE 90065
- Application / Permit
- 20014-20000-02098
- Plan Check / Job No.
- B20VN06881
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 12' X 15' REAR ADDITION, (N) 6'X 12' FRONT ADDITION, AND REMODEL TO SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/17/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Plan Check Approved | 3/22/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/22/2021 | APPLICANT |
| CofO in Progress | 4/25/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/21/2020 | NASHYA JENSEN |
| Low Impact Development | Cleared | 1/7/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/10/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 2/10/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2021 | CECILIO NAVARRO |
| GPI Written Notices | Cleared | 3/22/2021 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 3/22/2021 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/26/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/10/2021 | Partial Approval | PAUL BECKER |
| BUILDING-Rough-Frame | 5/27/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 5/27/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/18/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/20/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/20/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/19/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 8/19/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 9/10/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/10/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/21/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/1/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 2/1/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/1/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 2/1/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/1/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 4/25/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 4/25/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | HAMIK HARTOUNIAN |