12409 W SATICOY ST 91605
Certificate Information: 12409 W SATICOY ST 91605
- Application / Permit
- 20014-20000-02097
- Plan Check / Job No.
- B20VN06879
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 27'-8" X 30'-9" ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER WOOD FRAME PERSCRIPTIVE PROVISION.
- Permit Issued
- Issued on 8/30/2021
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2020 | SERGIO MUNIZ |
| Corrections Issued | 6/1/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 5/18/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/30/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 8/3/2021 | SERGIO MUNIZ |
| Plan Check Approved | 8/29/2021 | SERGIO MUNIZ |
| Issued | 8/30/2021 | APPLICANT |
| Building Plans Picked Up | 9/1/2021 | APPLICANT |
| CofO in Progress | 8/26/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/2/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 1/26/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/20/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 12/20/2021 | Partial Approval | WILLIAM KUEHN |
| Deputy Drilled-In Anchors | 1/7/2022 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 1/13/2022 | Corrections Issued | JOHN HAYES |
| METHANE-Barrier | 1/13/2022 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Subgrade | 1/13/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 1/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| METHANE-Barrier | 1/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| METHANE-Subgrade | 1/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/3/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 3/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 3/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 3/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| METHANE-Rough | 3/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 3/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/16/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Shower Pan | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 5/3/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Gas Test | 5/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 6/13/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 6/13/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 6/13/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 6/13/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 6/13/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 6/13/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 6/13/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| Final | 7/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Final | 8/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 8/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Final | 8/26/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |