2419 N CABOT ST 90031

Certificate Information: 2419 N CABOT ST 90031

Application / Permit
20014-20000-02093
Plan Check / Job No.
B20VN06867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add irr. 22'-6" x 32'-2" to and convert the detached garage into an Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 1/13/2021
Issuing Office
Current Status
CofO Issued on 3/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 SEAN SHAHMIRI
Corrections Issued 6/4/2020 SEAN SHAHMIRI
Building Plans Picked Up 6/22/2020 APPLICANT
Applicant returned to address corrections 11/4/2020 ANGELICA DAVE
Plan Check Approved 12/18/2020 ANGELICA MARTINEZ
Issued 1/13/2021 APPLICANT
CofO in Progress 9/21/2021 THOMAS LOGRASSO
CofO in Progress 9/21/2021 THOMAS LOGRASSO
Permit Finaled 3/13/2023 DANIEL ORRANTE
CofO Issued 3/13/2023 DANIEL ORRANTE
Permit Finaled 3/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction within easement Cleared 7/16/2020 WALTER RAMIREZ
Address approval Cleared 9/28/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/29/2020 JEANIE LAM
Sewer availability Cleared 9/29/2020 JEANIE LAM
Low Impact Development Cleared 11/23/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/17/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Gutierrez Brother Builders Inc; Lic. No.: 1057968-B 14519 PADDOCK STREET      SYLMAR, CA 91342
Engineer Nguyen,, Quynh Anh; Lic. No.: C58592 12000 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/11/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 2/11/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/18/2021 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/18/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/25/2021 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 2/25/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 2/25/2021 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/15/2021 Partial Approval SCOTT FINNILA
Green Building Rough 3/15/2021 Corrections Issued SCOTT FINNILA
MERV13>=Rough 3/15/2021 Partial Inspection SCOTT FINNILA
Wood Frame 3/15/2021 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 3/24/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 3/24/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 3/24/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 4/13/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/11/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 5/11/2021 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 5/11/2021 Approved KATHRYN BUTTERWORTH
Insulation 5/18/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/18/2021 Partial Approval THOMAS LOGRASSO
Shower Pan 5/18/2021 Approved THOMAS LOGRASSO
Drywall Nailing 5/25/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/25/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 8/13/2021 Corrections Issued THOMAS LOGRASSO
Final 8/13/2021 Corrections Issued THOMAS LOGRASSO
Gas Test 8/13/2021 Corrections Issued THOMAS LOGRASSO
Green Building Final 8/13/2021 Approved THOMAS LOGRASSO
HVAC-Final 8/13/2021 Partial Approval THOMAS LOGRASSO
MERV13>=Final 8/13/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 8/13/2021 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 8/13/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 8/18/2021 Approved THOMAS LOGRASSO
Gas Test 8/18/2021 Approved THOMAS LOGRASSO
HVAC-Final 8/18/2021 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 8/18/2021 Approved THOMAS LOGRASSO
HVAC-Final 8/23/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 8/27/2021 OK to Issue CofO THOMAS LOGRASSO
MERV13>=Final 9/21/2021 Approved THOMAS LOGRASSO