8144 N BROADLEAF AVE 91402

Certificate Information: 8144 N BROADLEAF AVE 91402

Application / Permit
20014-20000-02086
Plan Check / Job No.
B20VN06844
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'7"X31'0" FRONT ADDITION, 26'0"X8'0" SIDE ADDITION & REMODEL TO SFD AND 15'6"X25'0" PATIO ADDITION
Permit Issued
Issued on 9/18/2020
Issuing Office
Current Status
CofO Issued on 11/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 MARVEL DELACRUZ
Corrections Issued 6/21/2020 MARVEL DELACRUZ
Quality Review Completed 6/24/2020 STEVEN KIM
Building Plans Picked Up 6/24/2020 APPLICANT
Green Plans Picked Up 6/24/2020 APPLICANT
Applicant returned to address corrections 7/28/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 9/2/2020 MARVEL DELACRUZ
Applicant returned to address corrections 9/14/2020 MARVEL DELACRUZ
Plan Check Approved 9/18/2020 MARVEL DELACRUZ
Issued 9/18/2020 APPLICANT
CofO in Progress 10/5/2023 GREGG CUMMINGS
CofO Issued 11/16/2023 RUBEN SALAS
Permit Finaled 11/16/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2020 GABRIEL ROBLES
Sewer availability Cleared 6/25/2020 GABRIEL ROBLES
Low Impact Development Cleared 8/11/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 8/24/2020 ADRIAN CASTRO
Green Code Cleared 9/2/2020 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/21/2020 Approved GREGG CUMMINGS
Footing/Foundation/Slab 10/9/2020 Corrections Issued GREGG CUMMINGS
Deputy Drilled-In Anchors 10/13/2020 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 10/14/2020 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 10/28/2020 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 11/2/2020 Partial Approval GREGG CUMMINGS
Insulation 11/2/2020 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 6/15/2021 Corrections Issued MISAEL ESPARZA
HVAC-Rough 6/15/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 6/15/2021 Corrections Issued MISAEL ESPARZA
Wood Frame 6/15/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/23/2021 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 6/23/2021 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Approved GREGG CUMMINGS
Green Building Rough 6/23/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 6/23/2021 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 7/27/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 7/27/2021 Approved GREGG CUMMINGS
Insulation 8/17/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/17/2021 Partial Approval JAVIER RAMOS JR
Shower Pan 8/17/2021 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 8/24/2021 Approved JAVIER RAMOS JR
Shower Pan 8/24/2021 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 9/20/2021 Approved JUSTIN HAWLEY
Shower Pan 9/20/2021 Approved JUSTIN HAWLEY
ELECTRICAL-Final 11/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 11/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 11/28/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 11/28/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 11/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 11/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 11/28/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 11/28/2022 Approved CHRISTOPHER DELLEFIELD
Final 9/27/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 9/27/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 10/5/2023 Approved GREGG CUMMINGS
Final 10/5/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 10/5/2023 Approved GREGG CUMMINGS
PLUMBING-Final 10/5/2023 Approved GREGG CUMMINGS
Service/Power Release 10/5/2023 Approved GREGG CUMMINGS