4520 N EL ABACA PL 91356
Certificate Information: 4520 N EL ABACA PL 91356
- Application / Permit
- 20014-20000-02074
- Plan Check / Job No.
- B20VN06818
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 6' 10" X 23' 5" ADDITION TO (E) ATTACHED GARAGE AND INTERIOR REMODEL TO (E) KITCHEN/DINING/LIVING ROOM, ADD 1/2 BATHROOM & CONVERT (1) BEDROOM TO STUDY ROOM IN (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 7/7/2020
- Issuing Office
- Current Status
- CofO Issued on 4/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2020 | SERGIO MUNIZ |
| Corrections Issued | 6/3/2020 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/4/2020 | APPLICANT |
| Plan Check Approved | 6/19/2020 | GURUNATH NESARAJAH |
| Issued | 7/7/2020 | APPLICANT |
| CofO in Progress | 4/7/2021 | DAVID SANDOVAL |
| CofO Issued | 4/9/2021 | JOHN JANSON |
| Permit Finaled | 4/9/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 6/5/2020 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 6/11/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Patriot Contruction And Development; Lic. No.: 947058-B | 20335 VENTURA BL UNIT 235 WOODLAND HILLS, CA 91364 |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/14/2020 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 8/17/2020 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 8/20/2020 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 8/25/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/9/2020 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 11/9/2020 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 11/9/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 11/9/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Shower Pan | 11/9/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 11/18/2020 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 11/18/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/25/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 11/25/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 11/25/2020 | Approved | DAVID SANDOVAL |
| Insulation | 12/2/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 12/15/2020 | Approved | RONALD COWAN |
| Green Building Final | 3/25/2021 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2021 | SGSOV Not Ready | RONALD COWAN |
| Smoke Detectors | 3/25/2021 | Approved | RONALD COWAN |
| Final | 3/26/2021 | Corrections Issued | DAVID SANDOVAL |
| Final | 4/6/2021 | OK to Issue CofO | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Approved | DAVID SANDOVAL |