12925-12927 W MACNEIL ST 91342
Certificate Information: 12925-12927 W MACNEIL ST 91342
- Application / Permit
- 20014-20000-02069
- Plan Check / Job No.
- B20VN06800
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 5'-4" X 7'-3" NEW FULL BATH FOR (E) SFD, ADD IRREGULAR 15'-0" X 23'-0" FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Current Status
- CofO Issued on 8/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/28/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 6/1/2020 | APPLICANT |
| Applicant returned to address corrections | 6/9/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 7/29/2020 | OMAR GARNICA |
| Plan Check Approved | 9/3/2020 | OMAR GARNICA |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 1/4/2022 | JOHN HAYES |
| Permit Finaled | 8/31/2022 | DANIEL ORRANTE |
| CofO Issued | 8/31/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/31/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hold | Cleared | 7/30/2020 | JASON SHEETS |
| Address approval | Cleared | 8/3/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 8/3/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/3/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 8/24/2020 | BARTON HOLMES |
Contact Information
| Engineer | Nguyen,, Quynh Anh; Lic. No.: C58592 | 12000 MIRANDA ST VALLEY VILLAGE, CA 91607 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/29/2020 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/5/2020 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/5/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/19/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/19/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 11/19/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/19/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/24/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 11/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/24/2020 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/30/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/30/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/3/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 12/3/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/8/2020 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/8/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 12/8/2020 | Approved | MISAEL ESPARZA |
| Insulation | 1/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/4/2021 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 1/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 1/4/2021 | Partial Approval | MISAEL ESPARZA |
| Insulation | 1/6/2021 | Approved | MISAEL ESPARZA |
| Sewer | 1/6/2021 | Approved | MISAEL ESPARZA |
| Shower Pan | 1/6/2021 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 1/6/2021 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 1/15/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 1/15/2021 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 3/30/2021 | Conditional Approval | MISAEL ESPARZA |
| Final | 3/30/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 3/30/2021 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 3/30/2021 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 8/25/2021 | Approved | MISAEL ESPARZA |
| Final | 8/25/2021 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/20/2021 | Corrections Issued | JOHN HAYES |
| Final | 12/23/2021 | OK to Issue CofO | JOHN HAYES |