17155-17157 W GERMAIN ST 91344
Certificate Information: 17155-17157 W GERMAIN ST 91344
- Application / Permit
- 20014-20000-02068
- Plan Check / Job No.
- B20VN06799
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING 1 STORY SINGLE FAMILYDEWLLING AND NEW ADU (591SF zoning) CONNECTED BY NEW BREEZEWAY (215 SF) TO BECOME ONE SINGLE BUILDING. ALL WORK DONE PER WFPP. (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 2/11/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 6/20/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/6/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 1/21/2022 | AUNG SOE |
| Plan Check Approved | 1/24/2022 | AUNG SOE |
| Building Plans Picked Up | 2/2/2022 | APPLICANT |
| Issued | 2/11/2022 | APPLICANT |
| CofO in Progress | 8/8/2024 | KRISTEN BEVERIDGE |
| Permit Finaled | 10/4/2024 | JOHN JANSON |
| CofO Issued | 10/4/2024 | JOHN JANSON |
| Permit Finaled | 10/4/2024 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/9/2021 | MITESH PATEL |
| Address approval | Cleared | 10/26/2021 | LEE GUILBEAUX |
| ZI | Cleared | 10/28/2021 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/1/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/29/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | O'Brien,, Kathleen Anne; Lic. No.: C49498 | 1058 PACIFIC AVE SIMI VALLEY, CA 93065 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 4/14/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 4/14/2022 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 5/2/2022 | Approved | JEFFREY PARD |
| Deputy Drilled-In Anchors | 5/9/2022 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 5/16/2022 | Approved | JEFFREY PARD |
| Wood Frame | 6/13/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 10/20/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 10/20/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 10/20/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 10/20/2022 | Approved | JOHN KIDWELL |
| Insulation | 11/16/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 11/16/2022 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 2/24/2023 | Approved | JUSTIN HAWLEY |
| Gas Test | 11/28/2023 | Approved | JEFFREY PARD |
| Sewer | 11/28/2023 | Approved | JEFFREY PARD |
| Underground Mechanical | 11/28/2023 | Approved | JEFFREY PARD |
| Final | 7/26/2024 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 7/26/2024 | Approved | DAVID SCANTLIN |
| Green Building Final | 7/26/2024 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/26/2024 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 7/26/2024 | Approved | DAVID SCANTLIN |
| Final | 8/7/2024 | OK to Issue CofO | KRISTEN CAUSEY |
| Service/Power Release | 9/16/2024 | Approved | KRISTEN CAUSEY |