7408 N COLLETT AVE 91406

Certificate Information: 7408 N COLLETT AVE 91406

Application / Permit
20014-20000-02056
Plan Check / Job No.
B20VN06777
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-0" X 20'-0" DETACHED GARAGE AND ADD 20'-9" X 21'-6" FOR NEW ACCESSORY DWELLING UNIT. ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 06/16/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 9/17/2020
Issuing Office
Current Status
CofO Issued on 8/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 SEAN SHAHMIRI
Corrections Issued 6/5/2020 SEAN SHAHMIRI
Building Plans Picked Up 6/9/2020 APPLICANT
Applicant returned to address corrections 7/13/2020 JENNIFER LEE
Plan Check Approved 9/2/2020 JEROME MAGAT PALMA
Issued 9/17/2020 APPLICANT
CofO in Progress 7/1/2021 THOMAS WOODS
CofO Issued 8/4/2021 DAVID JAMES
Permit Finaled 8/4/2021 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 6/11/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/11/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/11/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 7/22/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/5/2020 GUILLERMO PETRA
Construction within easement Cleared 8/19/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/30/2020 Not Ready for Inspection THOMAS WOODS
Footing/Foundation/Slab 9/30/2020 Corrections Issued THOMAS WOODS
PLUMBING-Rough 9/30/2020 Partial Inspection THOMAS WOODS
Pre-Inspection 9/30/2020 Not Ready for Inspection THOMAS WOODS
Footing/Foundation/Slab 10/2/2020 Corrections Issued MICKEY YAMASHITA
Pre-Inspection 10/2/2020 Corrections Issued MICKEY YAMASHITA
Deputy Drilled-In Anchors 10/7/2020 Conditional Approval THOMAS WOODS
Excavation/Setback/Form/Re-Bar 10/8/2020 Not Ready for Inspection THOMAS WOODS
Footing/Foundation/Slab 10/8/2020 Corrections Issued THOMAS WOODS
Footing/Foundation/Slab 10/13/2020 Partial Approval THOMAS WOODS
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Approved THOMAS WOODS
Footing/Foundation/Slab 11/19/2020 Approved THOMAS WOODS
Wood Frame 11/19/2020 Approved THOMAS WOODS
Shower Pan 12/7/2020 Approved THOMAS WOODS
Pre-Inspection 12/8/2020 Not Ready for Inspection THOMAS WOODS
Deputy Drilled-In Anchors 12/9/2020 Approved THOMAS WOODS
ELECTRICAL-Rough 12/17/2020 Not Ready for Inspection THOMAS WOODS
ELECTRICAL-Rough 1/6/2021 Approved THOMAS WOODS
Gas Test 1/6/2021 Partial Approval THOMAS WOODS
Sewer 1/6/2021 Approved THOMAS WOODS
Deputy Drilled-In Anchors 1/13/2021 Approved THOMAS WOODS
Drywall Nailing 1/13/2021 Approved THOMAS WOODS
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Approved THOMAS WOODS
Gas Test 1/13/2021 Approved THOMAS WOODS
Insulation 1/13/2021 Approved THOMAS WOODS
PLUMBING-Rough 1/13/2021 Approved THOMAS WOODS
Final 3/24/2021 Not Ready for Inspection THOMAS WOODS
Gas Test 3/24/2021 Approved THOMAS WOODS
Green Building Final 3/24/2021 Not Ready for Inspection THOMAS WOODS
Green Building Rough 3/24/2021 Approved THOMAS WOODS
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Approved THOMAS WOODS
Smoke Detectors 3/24/2021 Not Ready for Inspection THOMAS WOODS
BUILDING-Rough-Frame 3/31/2021 Approved THOMAS WOODS
ELECTRICAL-Final 3/31/2021 Approved THOMAS WOODS
Final 3/31/2021 Conditional Approval THOMAS WOODS
Green Building Final 3/31/2021 Approved THOMAS WOODS
HVAC-Final 3/31/2021 Approved THOMAS WOODS
PLUMBING-Final 3/31/2021 Approved THOMAS WOODS
Smoke Detectors 3/31/2021 Approved THOMAS WOODS
Final 7/1/2021 OK to Issue CofO THOMAS WOODS