8119 N TILDEN AVE 91402
Certificate Information: 8119 N TILDEN AVE 91402
- Application / Permit
- 20014-20000-02048
- Plan Check / Job No.
- B20VN06746
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 26' - 1" X 14' - 9" IRREGULAR SHAPED ADDITION TO ENLARGE (E) ATTACHED 1-CAR GARAGE AND (N) 32'-10" X 29'-10" IRREGULAR SHAPED ADDITION TO ADD BEDROOM/FAMILY ROOM TO (E) SINGLE FAMILY DWELLING ALL WORK PER WFPP
- Permit Issued
- Issued on 8/31/2020
- Issuing Office
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/28/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 6/1/2020 | APPLICANT |
| Plan Check Approved | 8/26/2020 | JENNIFER LEE |
| Issued | 8/31/2020 | APPLICANT |
| CofO in Progress | 6/6/2023 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
| CofO Issued | 6/8/2023 | MICHAEL SMITH |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2020 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 8/13/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/24/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/28/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | 984 BROADWAY #302 CHULA VISTA, CA 91911 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/29/2020 | Partial Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/6/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/21/2020 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 10/21/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 10/21/2020 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2020 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/20/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 5/20/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 5/20/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/28/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 5/28/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 5/28/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 7/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 7/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 7/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 7/23/2021 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/2/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/2/2021 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 9/2/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 9/2/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 9/2/2021 | Partial Approval | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 9/15/2021 | Approved | GREGG CUMMINGS |
| Insulation | 10/4/2021 | Corrections Issued | WILLIAM WREN |
| Insulation | 11/3/2021 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 12/9/2021 | Approved | MATTHEW NELSON |
| Pre-Inspection | 12/16/2021 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 12/16/2021 | Not Ready for Inspection | DAVID MATSON |
| Sewer | 1/24/2022 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 1/24/2022 | Partial Approval | GREGG CUMMINGS |
| Insulation | 2/14/2022 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/22/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 2/22/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/1/2022 | Approved | ASHLEY THOMPSON |
| Insulation | 3/1/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 3/14/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 3/14/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/14/2022 | Not Ready for Inspection | WILLIAM WREN |
| Shower Pan | 3/14/2022 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 3/23/2022 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 3/23/2022 | Approved | GREGG CUMMINGS |
| Final | 12/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 12/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 12/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 1/6/2023 | Approved | DAVID MATSON |
| Special/Order Compliance | 1/6/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/15/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 2/15/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 2/15/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 2/15/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 2/15/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 2/15/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 2/28/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/28/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 2/28/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/3/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/30/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/30/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/30/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/30/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 6/6/2023 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 6/6/2023 | Approved | CHRISTOPHER DELLEFIELD |