1658 W 215TH ST 90501

Certificate Information: 1658 W 215TH ST 90501

Application / Permit
20014-20000-02047
Plan Check / Job No.
B20VN06744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 12'-7" X 24'-2" FOR NEW BEDROOM/BATHROOM/CLOSET TO AN (E) 1-STORY SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 6/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2020 APPLICANT
Assigned to Plan Check Engineer 5/15/2020 JENNIFER LEE
Corrections Issued 5/18/2020 JENNIFER LEE
Plan Check Approved 6/3/2020 JEFFREY TANGONAN
Issued 6/9/2020 LADBS
CofO in Progress 2/24/2021 JOHN KLARIN
Permit Finaled 2/27/2021 DEROLD HAUFF
CofO Issued 2/27/2021 DEROLD HAUFF
Permit Finaled 2/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/20/2020 ERIK BEASLEY
Roof/Waste drainage to street Cleared 5/20/2020 ERIK BEASLEY
Sewer availability Cleared 5/20/2020 ERIK BEASLEY

Contact Information

Contractor Guideline Builders Inc; Lic. No.: 1021305-B 18590 VENTURA BLVD UNIT 205      TARZANA, CA 91356

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2020 Approved JOHN KLARIN
Insulation 6/25/2020 Partial Inspection JOHN KLARIN
PLUMBING-Rough 6/25/2020 Partial Inspection JOHN KLARIN
Wood Frame 6/30/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/9/2020 Conditional Approval JOHN KLARIN
ELECTRICAL-Rough 7/9/2020 Corrections Issued JOHN KLARIN
Green Building Rough 7/9/2020 Approved JOHN KLARIN
PLUMBING-Rough 7/9/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 7/14/2020 Approved JOHN KLARIN
Insulation 7/14/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 7/14/2020 Approved JOHN KLARIN
Shower Pan 7/14/2020 Approved JOHN KLARIN
Drywall Nailing 7/15/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/15/2020 Approved EUGENE CASSIDY
Drywall Nailing 7/16/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/4/2020 Approved JOHN KLARIN
Final 8/4/2020 Corrections Issued JOHN KLARIN
Green Building Final 8/4/2020 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/4/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 8/4/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 12/30/2020 Not Ready for Inspection JOHN KLARIN
Pre-Inspection 12/30/2020 Not Ready for Inspection JOHN KLARIN
Final 1/4/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 1/4/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 2/23/2021 Approved JOHN KLARIN
Final 2/23/2021 OK to Issue CofO JOHN KLARIN
Green Building Final 2/23/2021 Approved JOHN KLARIN
HVAC-Final 2/23/2021 Approved JOHN KLARIN
PLUMBING-Final 2/23/2021 Approved JOHN KLARIN