3850 S NORTON AVE 90008

Certificate Information: 3850 S NORTON AVE 90008

Application / Permit
20014-20000-02038
Plan Check / Job No.
B20VN06709
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE SECOND STORY ADDITION WITH COVERED BALCONY OVER AND COVERED PATIO AT GROUND FLOOR TO (E) ONE STORY SFD _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 DAWN MC NULTY
Corrections Issued 6/13/2020 DAWN MC NULTY
Quality Review Completed 6/15/2020 CHON CHIO KUO
Building Plans Picked Up 6/15/2020 APPLICANT
Green Plans Picked Up 7/15/2020 APPLICANT
Applicant returned to address corrections 4/8/2021 DAWN MC NULTY
Applicant returned to address corrections 5/7/2021 DAWN MC NULTY
Plan Check Approved 6/28/2021 DAWN MC NULTY
Issued 7/1/2021 APPLICANT
CofO in Progress 7/30/2024 ANTHONY EGSON
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/4/2020 JAMES KHO
Sewer availability Cleared 8/4/2020 JAMES KHO
Low Impact Development Cleared 2/10/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/1/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Santos,, Michael Fernandez; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/8/2022 Approved HORACE FULTZ
PLUMBING-Rough 3/16/2022 Approved ANTHONY EGSON
Underground Mechanical 3/16/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 9/21/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 9/21/2022 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 9/27/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Approved ANTHONY EGSON
Green Building Rough 9/27/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/26/2022 Approved ANTHONY EGSON
Insulation 11/2/2022 Approved ANTHONY EGSON
Drywall Nailing 11/23/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 11/23/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/19/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/4/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 5/4/2023 Corrections Issued ANTHONY EGSON
Final 5/4/2023 Corrections Issued ANTHONY EGSON
Green Building Final 5/4/2023 Corrections Issued ANTHONY EGSON
HVAC-Final 5/4/2023 Approved ANTHONY EGSON
PLUMBING-Final 5/4/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/4/2023 SGSOV Approved ANTHONY EGSON
Smoke Detectors 5/4/2023 Approved ANTHONY EGSON
Final 6/6/2023 Corrections Issued ANTHONY EGSON
Green Building Final 6/6/2023 Not Ready for Inspection ANTHONY EGSON
Final 6/14/2023 Not Ready for Inspection ANTHONY EGSON
Green Building Final 6/14/2023 Not Ready for Inspection ANTHONY EGSON
Green Building Final 8/17/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 6/27/2024 Approved ANTHONY EGSON
Final 6/27/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Final 6/27/2024 Approved ANTHONY EGSON
Final 7/29/2024 OK to Issue CofO ANTHONY EGSON