12019 W ADDISON ST 91607

Certificate Information: 12019 W ADDISON ST 91607

Application / Permit
20014-20000-02023
Plan Check / Job No.
B20VN06649
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
IRR. SHAPED ADDITION OF 34'-0" x 19'-0" TO AND CONVERT (E) 18' X 18' GARAGE TO ACCESSORY DWELLING UNIT AND REMOVE 18' X 3'-6" PORTION OF (E) GARAGE PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 SEAN SHAHMIRI
Corrections Issued 6/12/2020 SEAN SHAHMIRI
Building Plans Picked Up 6/16/2020 APPLICANT
Applicant returned to address corrections 10/23/2020 RARES BODEA
Applicant returned to address corrections 1/22/2021 ROSENDO MEDINA
Applicant returned to address corrections 6/1/2021 SEAN SHAHMIRI
Plan Check Approved 6/18/2021 SEAN SHAHMIRI
Issued 7/14/2021 APPLICANT
CofO in Progress 2/4/2026 JAVIER RAMOS JR
Permit Finaled 3/10/2026 RUBEN SALAS
CofO Issued 3/10/2026 RUBEN SALAS
Permit Finaled 3/10/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/2/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 7/2/2020 ADRIAN CASTRO
Sewer availability Cleared 7/7/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/23/2020 ADRIAN CASTRO
Specific Plan Cleared 8/11/2020 ERIN NASH
Low Impact Development Cleared 5/19/2021 JORGE MEJIA LEMUS

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 17116 RAYMER STREET      NORTHRIDGE, CA 91325
Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/4/2021 Corrections Issued THOMAS FINNILA
Wood Frame 4/15/2022 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 4/21/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/26/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 4/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 4/27/2022 Approved MICHEL ABAJAN
HVAC-Rough 4/27/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 4/27/2022 Partial Inspection MICHEL ABAJAN
HVAC-Rough 5/2/2022 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Partial Approval THOMAS FINNILA
PLUMBING-Rough 5/4/2022 Approved THOMAS FINNILA
Rough-Elec/Plmb/HVAC 5/5/2022 Partial Approval THOMAS FINNILA
Wood Frame 5/5/2022 Partial Approval THOMAS FINNILA
Special/Order Compliance 5/12/2022 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 5/16/2022 Corrections Issued THOMAS FINNILA
Wood Frame 5/19/2022 Corrections Issued THOMAS FINNILA
Wood Frame 5/20/2022 Approved THOMAS FINNILA
Insulation 5/24/2022 Partial Approval DAVID MATSON
Insulation 6/1/2022 Corrections Issued THOMAS FINNILA
Insulation 6/2/2022 Approved THOMAS FINNILA
Drywall Nailing 6/7/2022 Approved CALEB MEISTER
Sewer 7/5/2022 Not Ready for Inspection CALEB MEISTER
Sewer 7/15/2022 Corrections Issued THOMAS FINNILA
Sewer 7/21/2022 Approved THOMAS FINNILA
PLUMBING-Rough 7/29/2022 Partial Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 7/29/2022 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 8/3/2022 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 11/2/2022 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 3/7/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 3/7/2023 Not Ready for Inspection JACK KARGODORIAN
Final 3/7/2023 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 3/7/2023 Approved JACK KARGODORIAN
Green Building Final 3/7/2023 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 3/7/2023 Approved JACK KARGODORIAN
HVAC-Final 3/7/2023 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 3/7/2023 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 3/7/2023 Approved JACK KARGODORIAN
Final 1/6/2026 Not Ready for Inspection CRAIG DAVIS
Green Building Final 1/6/2026 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Final 2/3/2026 Approved JAVIER RAMOS JR
Final 2/3/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 2/3/2026 Approved JAVIER RAMOS JR
HVAC-Final 2/3/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 2/3/2026 Approved JAVIER RAMOS JR
Service/Power Release 2/3/2026 Approved JAVIER RAMOS JR