17337 W CHASE ST 91325
Certificate Information: 17337 W CHASE ST 91325
- Application / Permit
- 20014-20000-01997
- Plan Check / Job No.
- B20VN06604
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) ATT. GARAGE AND ADD 17'-4" x 27'-4" TO ADD A NEW MASTER BEDRROM, BATHROOM AND CLOSET, AND REDESIGN (E) LAUNDRY ROOM AND REMODEL (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/5/2020
- Issuing Office
- Current Status
- CofO Issued on 12/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | SEAN SHAHMIRI |
| Corrections Issued | 5/28/2020 | SEAN SHAHMIRI |
| Building Plans Picked Up | 6/1/2020 | APPLICANT |
| Applicant returned to address corrections | 6/15/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/2/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 10/27/2020 | RAPHAEL ROSAS |
| Issued | 11/5/2020 | APPLICANT |
| CofO in Progress | 10/26/2021 | MARK JOHNSON |
| Permit Finaled | 12/13/2021 | RONALD MYRICK |
| CofO Issued | 12/13/2021 | RONALD MYRICK |
| Permit Finaled | 12/13/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/4/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 10/21/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/22/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Red Line Construction Inc; Lic. No.: 1047456-B | PO BOX 10508 CANOGA PARK, CA 91309 |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/12/2020 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 11/12/2020 | Partial Approval | MARK JOHNSON |
| Underground Mechanical | 11/12/2020 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 11/18/2020 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Partial Approval | MARK JOHNSON |
| Wood Frame | 12/7/2020 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Rough | 12/18/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 12/18/2020 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 12/23/2020 | Partial Inspection | MARK JOHNSON |
| Green Building Rough | 12/23/2020 | Approved | MARK JOHNSON |
| HVAC-Rough | 12/23/2020 | Not Ready for Inspection | MARK JOHNSON |
| Interior/Exterior Lathing | 12/23/2020 | Partial Inspection | MARK JOHNSON |
| Wood Frame | 12/23/2020 | Approved | MARK JOHNSON |
| HVAC-Rough | 12/28/2020 | Approved | MARK JOHNSON |
| Insulation | 12/28/2020 | Approved | MARK JOHNSON |
| Drywall Nailing | 1/4/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 1/4/2021 | Approved | MARK JOHNSON |
| Shower Pan | 1/4/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 2/1/2021 | Partial Approval | MARK JOHNSON |
| Grounding or Bonding | 2/1/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/6/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/6/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 8/6/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/6/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/6/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/6/2021 | Approved | JENNIFER RABUCHIN |
| Final | 8/20/2021 | Not Ready for Inspection | MARK JOHNSON |
| Final | 10/25/2021 | OK to Issue CofO | MARK JOHNSON |