12829 N HERRICK AVE 91342

Certificate Information: 12829 N HERRICK AVE 91342

Application / Permit
20014-20000-01966
Plan Check / Job No.
B20VN06510
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (20'-0"x 17'-0") TO AND CONVERT THE (E) (20'-0"x 14'-0") REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c) (d) and (g). WORK PER LA STD WFPP.
Permit Issued
Issued on 10/13/2020
Issuing Office
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 TROY DEGUZMAN
Corrections Issued 6/4/2020 TROY DEGUZMAN
Building Plans Picked Up 6/9/2020 APPLICANT
Plan Check Approved 10/13/2020 TROY DEGUZMAN
Issued 10/13/2020 APPLICANT
CofO in Progress 8/25/2025 KEVIN BERBERYAN
Permit Finaled 9/4/2025 RUBEN SALAS
CofO Issued 9/4/2025 RUBEN SALAS
Permit Finaled 9/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/31/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/31/2020 GABRIEL ROBLES
Sewer availability Cleared 10/5/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 10/13/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 6/11/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 6/11/2021 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 6/17/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/14/2024 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 3/14/2024 Not Ready for Inspection JENNIFER RABUCHIN
Final 3/14/2024 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 3/14/2024 Approved JENNIFER RABUCHIN
Green Building Final 3/14/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 3/14/2024 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 3/14/2024 Not Ready for Inspection JENNIFER RABUCHIN
Drywall Nailing 4/29/2024 Approved KEVIN BERBERYAN
Green Building Rough 4/29/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 8/22/2025 Approved KEVIN BERBERYAN
Final 8/22/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 8/22/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 8/22/2025 Approved KEVIN BERBERYAN