18015-18017 W COLLINS ST 91316

Certificate Information: 18015-18017 W COLLINS ST 91316

Application / Permit
20014-20000-01940
Plan Check / Job No.
B20VN06446
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 11'-0" X 20'-2" ATTACHED 1-CAR GARAGE AND ADD 12'-0" X 17'-10" FOR (N) ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (E). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/20/2020
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 DAWN MC NULTY
Corrections Issued 5/22/2020 DAWN MC NULTY
Building Plans Picked Up 5/28/2020 APPLICANT
Applicant returned to address corrections 6/25/2020 LUIS RINCON
Plan Check Approved 7/29/2020 JENNIFER LEE
Issued 8/20/2020 APPLICANT
CofO in Progress 3/23/2022 SEAN HAUPT
CofO Issued 5/4/2022 MICHAEL SMITH
Permit Finaled 5/4/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/8/2020 KATHLEEN HUGHEY
Eng Process Fee Ord 176,300 Cleared 6/9/2020 KATHLEEN HUGHEY
Roof/Waste drainage to street Cleared 6/29/2020 KATHLEEN HUGHEY
Sewer availability Cleared 6/30/2020 ROSE MARIE SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/4/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 8/4/2021 Partial Approval STEVEN BACK
Footing/Foundation/Slab 8/9/2021 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 8/11/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 10/13/2021 Approved SEAN HAUPT
ELECTRICAL-Rough 10/13/2021 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Approved SEAN HAUPT
Green Building Rough 10/13/2021 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 10/13/2021 Approved SEAN HAUPT
MERV13>=Rough 10/13/2021 Approved SEAN HAUPT
PLUMBING-Rough 10/13/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 10/18/2021 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 10/19/2021 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 10/25/2021 Approved SEAN HAUPT
Green Building Rough 10/25/2021 Approved SEAN HAUPT
Insulation 10/25/2021 Approved SEAN HAUPT
Drywall Nailing 11/1/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/12/2021 Approved JAVIER RAMOS JR
Shower Pan 11/12/2021 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/9/2022 Corrections Issued SEAN HAUPT
Final 3/9/2022 Corrections Issued SEAN HAUPT
Green Building Final 3/9/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 3/9/2022 Corrections Issued SEAN HAUPT
MERV13>=Final 3/9/2022 Approved SEAN HAUPT
PLUMBING-Final 3/9/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/9/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 3/9/2022 Approved SEAN HAUPT
ELECTRICAL-Final 3/23/2022 Approved SEAN HAUPT
Final 3/23/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 3/23/2022 Approved SEAN HAUPT
HVAC-Final 3/23/2022 Approved SEAN HAUPT
PLUMBING-Final 3/23/2022 Approved SEAN HAUPT