12549 N BROMONT AVE 91340

Certificate Information: 12549 N BROMONT AVE 91340

Application / Permit
20014-20000-01937
Plan Check / Job No.
B20VN06441
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 18' X 20' FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B) AND LAMC 12.22.A.33(C), (D) AND (G). ALL WORK PER WFPP.
Permit Issued
Issued on 9/16/2020
Issuing Office
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 DAWN MC NULTY
Corrections Issued 5/20/2020 DAWN MC NULTY
Building Plans Picked Up 5/22/2020 APPLICANT
Applicant returned to address corrections 6/12/2020 LUIS RINCON
Applicant returned to address corrections 8/18/2020 JENNIFER LEE
Plan Check Approved 9/15/2020 ANGELICA MARTINEZ
Issued 9/16/2020 APPLICANT
CofO in Progress 7/13/2021 MISAEL ESPARZA
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/20/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/20/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/23/2020 GABRIEL ROBLES
Sewer availability Cleared 7/23/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/23/2020 Approved MISAEL ESPARZA
Wood Frame 11/9/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/25/2020 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 1/14/2021 Corrections Issued MISAEL ESPARZA
Sewer 1/14/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 1/20/2021 Approved MISAEL ESPARZA
HVAC-Rough 1/20/2021 Conditional Approval MISAEL ESPARZA
Sewer 1/20/2021 Approved MISAEL ESPARZA
Wood Frame 1/20/2021 Approved MISAEL ESPARZA
Insulation 2/8/2021 Partial Approval MISAEL ESPARZA
Drywall Nailing 2/22/2021 Approved MISAEL ESPARZA
Green Building Rough 2/22/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/22/2021 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 6/22/2021 Partial Inspection MISAEL ESPARZA
PLUMBING-Final 6/22/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 7/6/2021 Approved MISAEL ESPARZA
Final 7/6/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 7/6/2021 Approved MISAEL ESPARZA
Green Building Final 7/6/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/6/2021 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 7/6/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/12/2021 Approved MISAEL ESPARZA
Final 7/12/2021 OK to Issue CofO MISAEL ESPARZA
Green Building Final 7/12/2021 Approved MISAEL ESPARZA
HVAC-Final 7/12/2021 Approved MISAEL ESPARZA
PLUMBING-Final 7/12/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved MISAEL ESPARZA
Special/Order Compliance 7/15/2021 Approved MISAEL ESPARZA