411 S MCCADDEN PL 90020
Certificate Information: 411 S MCCADDEN PL 90020
- Application / Permit
- 20014-20000-01930
- Plan Check / Job No.
- B20VN06427
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c)&(d)
- Permit Issued
- Issued on 12/1/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | CHON CHIO KUO |
| Corrections Issued | 6/3/2020 | CHON CHIO KUO |
| Quality Review Completed | 6/3/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/2/2020 | APPLICANT |
| Green Plans Picked Up | 7/2/2020 | APPLICANT |
| Applicant returned to address corrections | 10/15/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 11/9/2020 | CHON CHIO KUO |
| Plan Check Approved | 11/16/2020 | CHON CHIO KUO |
| Issued | 12/1/2020 | APPLICANT |
| CofO in Progress | 9/16/2021 | ARTHUR SARGSYAN |
| Permit Finaled | 1/13/2023 | DEROLD HAUFF |
| CofO Issued | 1/13/2023 | DEROLD HAUFF |
| Permit Finaled | 1/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2020 | CELINA MORENO |
| CPC | Cleared | 8/21/2020 | SUKI GERSHENHORN |
| CPC | Cleared | 8/21/2020 | SUKI GERSHENHORN |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2020 | CELINA MORENO |
| HPOZ | Cleared | 8/21/2020 | SUKI GERSHENHORN |
| ZI | Cleared | 8/21/2020 | SUKI GERSHENHORN |
| Hydrant and Access approval | Cleared | 9/23/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 11/10/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/12/2020 | RIDWAN HARDY |
| Green Code | Cleared | 11/12/2020 | CHON CHIO KUO |
| Roof/Waste drainage to street | Cleared | 11/13/2020 | CELINA MORENO |
Contact Information
| Contractor | Blackfox; Lic. No.: 788491-B | 4918 W 138TH STREET HAWTHORNE, CA 90250 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/7/2020 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/16/2020 | Partial Approval | STUART CHAPMAN |
| METHANE-Barrier | 12/16/2020 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 12/16/2020 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/24/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 12/24/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/2/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/2/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 2/2/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 2/2/2021 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Rough | 2/2/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/2/2021 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 2/8/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 3/2/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/2/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/2/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 3/2/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/12/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/22/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/13/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 4/13/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 4/13/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 4/13/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/13/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 6/25/2021 | Approved | RICHARD STEINBACH |
| Final | 6/25/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Green Building Final | 6/25/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| HVAC-Final | 6/25/2021 | Corrections Issued | RICHARD STEINBACH |
| PLUMBING-Final | 6/25/2021 | Corrections Issued | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Approved | RICHARD STEINBACH |
| Smoke Detectors | 6/25/2021 | Approved | RICHARD STEINBACH |
| Final | 9/2/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| Green Building Final | 9/2/2021 | Approved | ARTHUR SARGSYAN |
| Pre-Inspection | 11/3/2021 | Approved | ARTHUR SARGSYAN |
| Pre-Inspection | 11/5/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Special/Order Compliance | 10/17/2022 | Approved | MICHAEL LEWIS |