2208 S GLENCOE AVE 90291

Certificate Information: 2208 S GLENCOE AVE 90291

Application / Permit
20014-20000-01920
Plan Check / Job No.
B20VN06391
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING RECREATION ROOM TO ADU PER LAMC 12.22 A.33(c) AND (d) ATTACHED TO EXISTING GARAGE
Permit Issued
Issued on 5/17/2021
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 CRYSTEL MAALOUF
Corrections Issued 6/16/2020 CRYSTEL MAALOUF
Quality Review Completed 7/15/2020 TU HUA
Building Plans Picked Up 7/22/2020 APPLICANT
Green Plans Picked Up 8/4/2020 APPLICANT
Applicant returned to address corrections 11/16/2020 CRYSTEL MAALOUF
Plan Check Approved 3/16/2021 CRYSTEL MAALOUF
Issued 5/17/2021 APPLICANT
CofO in Progress 8/24/2023 DAVID FEILER
Permit Finaled 8/29/2023 DANIEL ORRANTE
CofO Issued 8/29/2023 DANIEL ORRANTE
Permit Finaled 8/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/25/2021 DINAH GARIN
Sewer availability Cleared 1/25/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/26/2021 DINAH GARIN
CPC Cleared 2/25/2021 ANNA VIDAL
CPC Cleared 2/25/2021 ANNA VIDAL
CPC Cleared 2/25/2021 ANNA VIDAL
Green Code Cleared 3/9/2021 CRYSTEL MAALOUF
Specific Plan Cleared 3/11/2021 PEDRO AYALA

Contact Information

Contractor H A S Construction Inc; Lic. No.: 538538-B 11272 WASHINGTON PL      CULVER CITY, CA 90230
Engineer Loayza,, Miguel Antonio; Lic. No.: C26290 20062 MERRIDY STREET      CHATSWORTH, CA 91311

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 5/27/2021 Partial Approval JOHNNY MIRANDA
Sewer 5/27/2021 Corrections Issued JOHNNY MIRANDA
Sewer 6/8/2021 Not Ready for Inspection JOHNNY MIRANDA
Special/Order Compliance 6/8/2021 Approved PIERRE VEGA
Sewer 6/11/2021 Approved PIERRE VEGA
Underground Mechanical 6/11/2021 Approved PIERRE VEGA
Footing/Foundation/Slab 6/17/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 7/8/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 7/8/2021 Not Ready for Inspection JOHNNY MIRANDA
Underground Mechanical 7/8/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 7/15/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 7/15/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 7/15/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 7/19/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 7/26/2021 Approved JOHNNY MIRANDA
Green Building Rough 7/26/2021 Approved JOHNNY MIRANDA
Insulation 7/26/2021 Approved JOHNNY MIRANDA
Drywall Nailing 8/5/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 8/5/2021 Approved MORRIS JACKSON
Pre-Inspection 8/5/2021 Partial Inspection SHAVONNE ESPINOZA
ELECTRICAL-Final 9/13/2021 Approved JOHNNY MIRANDA
Final 9/30/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 9/30/2021 Corrections Issued JOHNNY MIRANDA
HVAC-Final 9/30/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 9/30/2021 Approved JOHNNY MIRANDA
Final 10/12/2021 OK to Issue CofO JOHNNY MIRANDA
Green Building Final 10/12/2021 Approved JOHNNY MIRANDA
HVAC-Final 10/12/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 10/12/2021 Approved JOHNNY MIRANDA