3169 N OAKSHIRE DR 90068

Certificate Information: 3169 N OAKSHIRE DR 90068

Application / Permit
20014-20000-01919
Plan Check / Job No.
B20VN06390
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION / REMODEL TO (E) ON STORY SFD TO ADD A DRESSING ROOM AND BATHROOM TO 2ND LEVEL
Permit Issued
Issued on 9/22/2020
Issuing Office
Current Status
CofO Issued on 4/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 MOHAMMAD ESMAILI
Corrections Issued 6/19/2020 MOHAMMAD ESMAILI
Quality Review Completed 6/26/2020 OMID HEDAYAT
Building Plans Picked Up 7/10/2020 APPLICANT
Green Plans Picked Up 7/10/2020 APPLICANT
Plan Check Approved 9/4/2020 MOHAMMAD ESMAILI
Issued 9/22/2020 APPLICANT
CofO in Progress 10/15/2022 BRIAN SULLIVAN
Permit Finaled 4/1/2023 DANIEL ORRANTE
CofO Issued 4/1/2023 DANIEL ORRANTE
Permit Finaled 4/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/23/2020 GABRIEL ROBLES
Sewer availability Cleared 7/23/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/28/2020 GABRIEL ROBLES
Specific Plan Cleared 8/6/2020 TRACY WILLIAMS
ZI Cleared 8/6/2020 TRACY WILLIAMS
Distance to fire station Cleared 8/18/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 9/4/2020 MOHAMMAD ESMAILI

Contact Information

Contractor Kempler & Company Incorporated; Lic. No.: 562533-B 14731 SUTTON STREET      SHERMAN OAKS, CA 91403
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2020 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 12/22/2020 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/1/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Approved BRIAN SULLIVAN
Green Building Rough 3/16/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 4/29/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 4/29/2021 Approved BRIAN SULLIVAN
HVAC-Rough 4/29/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/29/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 5/7/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 5/7/2021 Partial Approval BRIAN SULLIVAN
Shower Pan 5/7/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 5/11/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 5/11/2021 Approved BRIAN SULLIVAN
Shower Pan 5/11/2021 Approved BRIAN SULLIVAN
Drywall Nailing 5/28/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 9/23/2022 Approved BRIAN SULLIVAN
Final 9/23/2022 Corrections Issued BRIAN SULLIVAN
Green Building Final 9/23/2022 Approved BRIAN SULLIVAN
HVAC-Final 9/23/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 9/23/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 9/23/2022 Approved BRIAN SULLIVAN
Final 10/14/2022 OK to Issue CofO BRIAN SULLIVAN