14829 W HAGAR ST 91345

Certificate Information: 14829 W HAGAR ST 91345

Application / Permit
20014-20000-01912
Plan Check / Job No.
B20VN06371
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 18' X 20' DETACHED GARAGE AND ADDITION OF IRREGULAR 22'-9" X 37.75' TO CREATE AN ACCESSORY DWELLING UNIT AND ADDITION OF A 3'-9" X 7'-1" ATTACHED PATIO COVER. WORK PER WFPP. CONVERSION PER LAMC 12.22 A.33(c) AND (d). SEE COMMENTS.
Permit Issued
Issued on 10/22/2020
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 DAWN MC NULTY
Corrections Issued 5/20/2020 DAWN MC NULTY
Building Plans Picked Up 5/27/2020 APPLICANT
Applicant returned to address corrections 6/5/2020 RAPHAEL ROSAS
Applicant returned to address corrections 6/18/2020 LUIS RINCON
Applicant returned to address corrections 7/7/2020 LUIS RINCON
Applicant returned to address corrections 9/30/2020 LUIS RINCON
Plan Check Approved 10/16/2020 LUIS RINCON
Issued 10/22/2020 APPLICANT
CofO in Progress 2/25/2022 JENNIFER RABUCHIN
Permit Finaled 3/16/2022 RONALD MYRICK
CofO Issued 3/16/2022 RONALD MYRICK
Permit Finaled 3/16/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 5/27/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/27/2020 ADRIAN CASTRO
Sewer availability Cleared 5/27/2020 ADRIAN CASTRO
Permit Cleared 7/10/2020 ADRIAN CASTRO
Construction near power lines Cleared 7/29/2020 RIDWAN HARDY
Construction within easement Cleared 7/29/2020 RIDWAN HARDY
Low Impact Development Cleared 9/10/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/11/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/27/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/27/2020 Not Ready for Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 11/2/2020 Approved JENNIFER RABUCHIN
Special/Order Compliance 11/2/2020 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/20/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/20/2020 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Approved JENNIFER RABUCHIN
Gas Test 11/20/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 11/20/2020 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 11/20/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/20/2020 Approved JENNIFER RABUCHIN
Sewer 11/20/2020 Approved JENNIFER RABUCHIN
Underground Mechanical 11/20/2020 Partial Approval JENNIFER RABUCHIN
Wood Frame 11/20/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/24/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 11/24/2020 Approved JENNIFER RABUCHIN
Insulation 11/25/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 11/30/2020 Approved JENNIFER RABUCHIN
Green Building Rough 11/30/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/30/2020 Approved JENNIFER RABUCHIN
Final 1/25/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 1/25/2021 Approved JENNIFER RABUCHIN
Green Building Final 1/25/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/25/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/25/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/8/2021 Approved JENNIFER RABUCHIN
Final 2/8/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/8/2021 Approved JENNIFER RABUCHIN
HVAC-Final 2/8/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/8/2021 Approved JENNIFER RABUCHIN
Final 2/25/2022 OK to Issue CofO JENNIFER RABUCHIN