8031-8033 N MCDERMOTT AVE 91335

Certificate Information: 8031-8033 N MCDERMOTT AVE 91335

Application / Permit
20014-20000-01911
Plan Check / Job No.
B20VN06370
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 18' X 20' ATTACHED GARAGE AND ADD 10' X 18' TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/10/2020
Issuing Office
Current Status
CofO Issued on 10/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 5/13/2020 RAPHAEL ROSAS
Corrections Issued 5/14/2020 RAPHAEL ROSAS
Applicant returned to address corrections 10/27/2020 RAPHAEL ROSAS
Issued 11/10/2020 APPLICANT
CofO in Progress 10/26/2021 VINCENT HANLEY
Permit Finaled 10/30/2021 MICHAEL SMITH
CofO Issued 10/30/2021 MICHAEL SMITH
Permit Finaled 10/30/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/20/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/21/2020 GUILLERMO PETRA
Sewer availability Cleared 5/21/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 10/14/2020 GUILLERMO PETRA
Low Impact Development Cleared 10/15/2020 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Owner-Builder       ,
Engineer Azarbin,, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/11/2020 Partial Approval VINCENT HANLEY
Sewer 12/11/2020 Approved VINCENT HANLEY
Footing/Foundation/Slab 12/15/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/14/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/15/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/15/2021 Approved VINCENT HANLEY
Green Building Rough 4/15/2021 Approved VINCENT HANLEY
HVAC-Rough 4/15/2021 Approved VINCENT HANLEY
PLUMBING-Rough 4/15/2021 Approved VINCENT HANLEY
Insulation 4/27/2021 Approved VINCENT HANLEY
Drywall Nailing 5/3/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/3/2021 Approved VINCENT HANLEY
Shower Pan 5/3/2021 Approved VINCENT HANLEY
Service/Power Release 5/4/2021 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 8/4/2021 Approved VINCENT HANLEY
Final 8/4/2021 Corrections Issued VINCENT HANLEY
Gas Test 8/4/2021 Approved VINCENT HANLEY
Green Building Final 8/4/2021 Approved VINCENT HANLEY
HVAC-Final 8/4/2021 Approved VINCENT HANLEY
PLUMBING-Final 8/4/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 8/4/2021 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 8/4/2021 Approved VINCENT HANLEY
Final 9/3/2021 Not Ready for Inspection VINCENT HANLEY
Final 10/26/2021 OK to Issue CofO VINCENT HANLEY