2310 N HILLHURST AVE 90027
Certificate Information: 2310 N HILLHURST AVE 90027
- Application / Permit
- 20014-20000-01894
- Plan Check / Job No.
- B20VN06283
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND ADD ( 37'-11"x 29'-4") IRR SHAPE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER LA STD WFPP.
- Permit Issued
- Issued on 2/2/2021
- Issuing Office
- Current Status
- CofO Issued on 9/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/26/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 5/27/2020 | APPLICANT |
| Plan Check Approved | 1/19/2021 | TROY DEGUZMAN |
| Issued | 2/2/2021 | APPLICANT |
| CofO in Progress | 8/22/2022 | JOSEPH MCGARRY |
| Permit Finaled | 9/2/2022 | DEROLD HAUFF |
| CofO Issued | 9/2/2022 | DEROLD HAUFF |
| Permit Finaled | 9/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2020 | CELINA MORENO |
| Sewer availability | Cleared | 6/22/2020 | CELINA MORENO |
| Low Impact Development | Cleared | 7/2/2020 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 1/11/2021 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 1/12/2021 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 1/19/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 1/19/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/6/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/25/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/11/2021 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 6/11/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/2/2021 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Green Building Rough | 8/2/2021 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 9/2/2021 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/2/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 9/2/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/2/2021 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 9/2/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/10/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 9/10/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/8/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 12/8/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 12/17/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/17/2021 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 12/30/2021 | Approved | JOSEPH MCGARRY |
| Gas Test | 12/30/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/30/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 12/30/2021 | Approved | JOSEPH MCGARRY |
| Pre-Inspection | 5/12/2022 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 5/13/2022 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 5/13/2022 | Partial Approval | JOSEPH MCGARRY |
| Final | 7/15/2022 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 7/15/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 7/15/2022 | Approved | JOSEPH MCGARRY |
| Final | 7/19/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Gas Test | 7/19/2022 | Approved | JOSEPH MCGARRY |
| Final | 8/10/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 8/16/2022 | OK to Issue CofO | JOSEPH MCGARRY |