18407 W FRIAR ST 91335
Certificate Information: 18407 W FRIAR ST 91335
- Application / Permit
- 20014-20000-01893
- Plan Check / Job No.
- B20VN06277
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (2 OF 2) ADDITION AND CONVERT DETACHED GARGE TO NEW ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 9/17/2020
- Issuing Office
- Current Status
- CofO Issued on 7/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/24/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 6/18/2020 | STEVEN KIM |
| Building Plans Picked Up | 6/23/2020 | APPLICANT |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Plan Check Approved | 9/4/2020 | MOHAMMAD ESMAILI |
| Issued | 9/17/2020 | APPLICANT |
| CofO in Progress | 7/27/2021 | STEVEN BACK |
| Permit Finaled | 7/29/2021 | JOHN JANSON |
| CofO Issued | 7/29/2021 | JOHN JANSON |
| Permit Finaled | 7/29/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 7/14/2020 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 7/14/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/14/2020 | GABRIEL ROBLES |
| ZA Case | Cleared | 7/14/2020 | ANNA VIDAL |
| ZI | Cleared | 7/14/2020 | ANNA VIDAL |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Wrap Development Group Inc; Lic. No.: 1029313-B | 2205 TORRANCE ST SIMI VALLEY, CA 93065 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/5/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 10/6/2020 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 10/21/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 10/21/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 1/19/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/19/2021 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 1/19/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 1/19/2021 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 1/19/2021 | Approved | BRENDAN LOONEY |
| Sewer | 1/19/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 1/19/2021 | Approved | BRENDAN LOONEY |
| Sewer | 1/26/2021 | Approved | RONALD COWAN |
| Wood Frame | 1/26/2021 | Approved | RONALD COWAN |
| Green Building Rough | 2/1/2021 | Approved | STEVEN BACK |
| Insulation | 2/1/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 2/5/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 2/5/2021 | Partial Approval | STEVEN BACK |
| Interior/Exterior Lathing | 2/22/2021 | Approved | STEVEN BACK |
| Shower Pan | 2/22/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 5/13/2021 | Corrections Issued | STEVEN BACK |
| Final | 5/13/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 5/13/2021 | No Access for Inspection | STEVEN BACK |
| HVAC-Final | 5/13/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 5/13/2021 | No Access for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Not Ready | STEVEN BACK |
| Service/Power Release | 5/13/2021 | No Access for Inspection | STEVEN BACK |
| Smoke Detectors | 5/13/2021 | No Access for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 6/25/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 6/25/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 6/25/2021 | Approved | STEVEN BACK |
| HVAC-Final | 6/25/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Final | 6/25/2021 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 6/25/2021 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 6/25/2021 | Approved | STEVEN BACK |
| Final | 7/27/2021 | OK to Issue CofO | STEVEN BACK |