18407 W FRIAR ST 91335

Certificate Information: 18407 W FRIAR ST 91335

Application / Permit
20014-20000-01893
Plan Check / Job No.
B20VN06277
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(2 OF 2) ADDITION AND CONVERT DETACHED GARGE TO NEW ACCESSORY DWELLING UNIT
Permit Issued
Issued on 9/17/2020
Issuing Office
Current Status
CofO Issued on 7/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 MOHAMMAD ESMAILI
Corrections Issued 5/24/2020 MOHAMMAD ESMAILI
Quality Review Completed 6/18/2020 STEVEN KIM
Building Plans Picked Up 6/23/2020 APPLICANT
Green Plans Picked Up 6/23/2020 APPLICANT
Plan Check Approved 9/4/2020 MOHAMMAD ESMAILI
Issued 9/17/2020 APPLICANT
CofO in Progress 7/27/2021 STEVEN BACK
Permit Finaled 7/29/2021 JOHN JANSON
CofO Issued 7/29/2021 JOHN JANSON
Permit Finaled 7/29/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/14/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/14/2020 GABRIEL ROBLES
Green Code Cleared 7/14/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 7/14/2020 GABRIEL ROBLES
Sewer availability Cleared 7/14/2020 GABRIEL ROBLES
ZA Case Cleared 7/14/2020 ANNA VIDAL
ZI Cleared 7/14/2020 ANNA VIDAL

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor Wrap Development Group Inc; Lic. No.: 1029313-B 2205 TORRANCE ST      SIMI VALLEY, CA 93065

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/5/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 10/6/2020 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 10/21/2020 Approved STEVEN BACK
Footing/Foundation/Slab 10/21/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 1/19/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 1/19/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Approved BRENDAN LOONEY
Green Building Rough 1/19/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 1/19/2021 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 1/19/2021 Approved BRENDAN LOONEY
Sewer 1/19/2021 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 1/19/2021 Approved BRENDAN LOONEY
Sewer 1/26/2021 Approved RONALD COWAN
Wood Frame 1/26/2021 Approved RONALD COWAN
Green Building Rough 2/1/2021 Approved STEVEN BACK
Insulation 2/1/2021 Approved STEVEN BACK
Drywall Nailing 2/5/2021 Approved STEVEN BACK
Interior/Exterior Lathing 2/5/2021 Partial Approval STEVEN BACK
Interior/Exterior Lathing 2/22/2021 Approved STEVEN BACK
Shower Pan 2/22/2021 Approved STEVEN BACK
ELECTRICAL-Final 5/13/2021 Corrections Issued STEVEN BACK
Final 5/13/2021 Corrections Issued STEVEN BACK
Green Building Final 5/13/2021 No Access for Inspection STEVEN BACK
HVAC-Final 5/13/2021 Corrections Issued STEVEN BACK
PLUMBING-Final 5/13/2021 No Access for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/13/2021 SGSOV Not Ready STEVEN BACK
Service/Power Release 5/13/2021 No Access for Inspection STEVEN BACK
Smoke Detectors 5/13/2021 No Access for Inspection STEVEN BACK
ELECTRICAL-Final 6/25/2021 Not Ready for Inspection STEVEN BACK
Final 6/25/2021 Corrections Issued STEVEN BACK
Green Building Final 6/25/2021 Approved STEVEN BACK
HVAC-Final 6/25/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Final 6/25/2021 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/25/2021 SGSOV Approved STEVEN BACK
Service/Power Release 6/25/2021 Not Ready for Inspection STEVEN BACK
Smoke Detectors 6/25/2021 Approved STEVEN BACK
Final 7/27/2021 OK to Issue CofO STEVEN BACK