11316-11318 N TAMARACK AVE 91340

Certificate Information: 11316-11318 N TAMARACK AVE 91340

Application / Permit
20014-20000-01879
Plan Check / Job No.
B20VN06235
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' X 30' ATTACHED GARAGE AND ADD 5' X 30' FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (E). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/7/2020
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 MOHAMMAD ESMAILI
Corrections Issued 5/15/2020 MOHAMMAD ESMAILI
Building Plans Picked Up 5/20/2020 APPLICANT
Applicant returned to address corrections 6/16/2020 HAYATO TSUCHIYA
Plan Check Approved 8/4/2020 JENNIFER LEE
Issued 8/7/2020 APPLICANT
CofO in Progress 11/30/2022 JENNIFER RABUCHIN
CofO in Progress 12/1/2022 JENNIFER RABUCHIN
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/26/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/26/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 5/26/2020 GUILLERMO PETRA
Sewer availability Cleared 5/26/2020 GUILLERMO PETRA
ZI Cleared 6/4/2020 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C88998       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2020 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 10/15/2020 Approved JENNIFER RABUCHIN
METHANE-Subgrade 10/15/2020 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 5/5/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/7/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/7/2021 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 6/7/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/13/2021 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 8/23/2021 Approved JENNIFER RABUCHIN
Special/Order Compliance 8/23/2021 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 11/1/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 1/3/2022 Approved JENNIFER RABUCHIN
Insulation 1/3/2022 Approved JENNIFER RABUCHIN
Gas Test 1/21/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 1/26/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/9/2022 Not Ready for Inspection JENNIFER RABUCHIN
Final 8/9/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/9/2022 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 8/9/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 8/9/2022 Not Ready for Inspection JENNIFER RABUCHIN
Final 10/13/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/13/2022 Approved JENNIFER RABUCHIN
Smoke Detectors 10/13/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/16/2022 Approved JENNIFER RABUCHIN
Final 11/16/2022 OK to Issue CofO JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/1/2022 Approved JENNIFER RABUCHIN
Final 12/1/2022 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 12/1/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/1/2022 Approved JENNIFER RABUCHIN