10854 N DELIBAN AVE 91042

Certificate Information: 10854 N DELIBAN AVE 91042

Application / Permit
20014-20000-01874
Plan Check / Job No.
B20VN06225
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
11'-10" X 11'-7" L-SHAPED ADDITION TO (E) SFD TO EXTEND DINING ROOM
Permit Issued
Issued on 7/10/2020
Issuing Office
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2020 APPLICANT
Assigned to Plan Check Engineer 5/4/2020 ROSENDO MEDINA
Corrections Issued 5/5/2020 ROSENDO MEDINA
Applicant returned to address corrections 6/2/2020 ROSENDO MEDINA
Applicant returned to address corrections 6/24/2020 JEROME MAGAT PALMA
Plan Check Approved 6/25/2020 JEROME MAGAT PALMA
Issued 7/10/2020 APPLICANT
Building Plans Picked Up 7/17/2020 APPLICANT
CofO in Progress 4/30/2021 MATTHEW NELSON
Permit Finaled 8/7/2021 MICHAEL SMITH
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/22/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 6/10/2020 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 6/24/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/5/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Approved MATTHEW NELSON
Wood Frame 11/16/2020 Not Ready for Inspection MATTHEW NELSON
Drywall Nailing 11/20/2020 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/10/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 12/10/2020 Approved MATTHEW NELSON
Green Building Rough 12/10/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/10/2020 Approved MATTHEW NELSON
Insulation 12/14/2020 Approved MATTHEW NELSON
Drywall Nailing 12/17/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 12/21/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 3/3/2021 Approved MATTHEW NELSON
Final 3/3/2021 Corrections Issued MATTHEW NELSON
Green Building Final 3/3/2021 Approved MATTHEW NELSON
Smoke Detectors 3/3/2021 Approved MATTHEW NELSON
Final 4/7/2021 Not Ready for Inspection MATTHEW NELSON
Final 4/30/2021 OK to Issue CofO MATTHEW NELSON