NEW 16' X 15'1-1/2" AND 8'2" X 16'9-1/2" ADDITIONS TO AND CONVERT THE (E) 18'3-1/2" X 18'3-1/2" TWO CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33 (C) AND (E) , ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 RARES BODEA
Corrections Issued 6/8/2020 RARES BODEA
Building Plans Picked Up 6/9/2020 APPLICANT
No Progress 6/24/2020 RARES BODEA
Plan Check Approved 10/9/2020 RARES BODEA
Issued 11/2/2020 APPLICANT
CofO in Progress 9/16/2022 RICHARD DOCKUS
Permit Finaled 11/19/2022 MICHAEL SMITH
CofO Issued 11/19/2022 MICHAEL SMITH
Permit Finaled 11/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/10/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 6/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/15/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/15/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 9/24/2020 MITESH PATEL

Contact Information

Contractor D A Construction Inc; Lic. No.: 1051022-B 14320 VENTURA BOULEVARD   UNIT 282    SHERMAN OAKS, CA 91423
Engineer Sin,, John P; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/23/2022 Approved RICHARD DOCKUS
Underground Mechanical 3/4/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 3/29/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 3/29/2022 Corrections Issued RAUL OLAGI
HVAC-Rough 3/29/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/29/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 4/4/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 4/4/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 4/4/2022 Approved RICHARD DOCKUS
HVAC-Rough 4/4/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 4/4/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 4/11/2022 Corrections Issued ALAN MORELOS
PLUMBING-Rough 4/11/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 4/14/2022 Partial Approval ALAN MORELOS
BUILDING-Rough-Frame 4/19/2022 Corrections Issued MICHAEL TEMPLE
Insulation 4/19/2022 Corrections Issued MICHAEL TEMPLE
Insulation 4/20/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 4/25/2022 No Access for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/28/2022 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 5/11/2022 Approved ALAN MORELOS
Shower Pan 5/11/2022 Corrections Issued ALAN MORELOS
Shower Pan 5/19/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 5/27/2022 Conditional Approval RICHARD DOCKUS
ELECTRICAL-Rough 5/27/2022 Partial Approval RICHARD DOCKUS
Insulation 5/27/2022 Conditional Approval RICHARD DOCKUS
BUILDING-Rough-Frame 6/6/2022 Approved RICHARD DOCKUS
Insulation 6/6/2022 Approved RICHARD DOCKUS
Drywall Nailing 6/14/2022 Approved MATT KELLERMAN
Green Building Final 8/3/2022 Approved RICHARD DOCKUS
PLUMBING-Final 8/3/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 8/3/2022 Approved RICHARD DOCKUS
Final 8/15/2022 Corrections Issued RICHARD DOCKUS
Final 9/1/2022 Not Ready for Inspection RICHARD DOCKUS
Final 9/12/2022 Corrections Issued JACK KARGODORIAN
Final 9/16/2022 OK to Issue CofO RICHARD DOCKUS