917 1/2 E 76TH PL 90001

Certificate Information: 917 1/2 E 76TH PL 90001

Application / Permit
20014-20000-01862
Plan Check / Job No.
B20VN06204
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 11'6" X 20'6" TO AND CONVERT (E) 18'' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A33(C) AND (E) , ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/21/2020
Issuing Office
Current Status
CofO Issued on 9/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2020 APPLICANT
Assigned to Plan Check Engineer 6/24/2020 RARES BODEA
Corrections Issued 6/24/2020 RARES BODEA
Building Plans Picked Up 6/26/2020 APPLICANT
Plan Check Approved 9/18/2020 RARES BODEA
Issued 9/21/2020 APPLICANT
CofO in Progress 8/24/2021 HORACE FULTZ
CofO Issued 9/2/2021 DEROLD HAUFF
Permit Finaled 9/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/23/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 7/23/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 7/24/2020 THOMAS LANG
Sewer availability Cleared 7/24/2020 THOMAS LANG
Construction near power lines Cleared 8/31/2020 RIDWAN HARDY

Contact Information

Contractor Eco Home Builders; Lic. No.: 1018718-B PO BOX 14      SUN VALLEY, CA 91353
Engineer Rodriguez,, Jacob; Lic. No.: S5084 8206 ENCINO AVE      NORTHRIDGE, CA 91325

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2021 Partial Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 2/5/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 2/5/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/18/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 2/18/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/19/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 3/19/2021 Approved EUGENE CASSIDY
Insulation 4/8/2021 Approved RUBEN SALAS
Interior/Exterior Lathing 4/8/2021 Partial Approval RUBEN SALAS
Service/Power Release 4/8/2021 Partial Inspection RUBEN SALAS
Drywall Nailing 4/23/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 4/23/2021 Approved ALEJANDRO DE ARTOLA
Sewer 5/28/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 6/7/2021 Approved EUGENE CASSIDY
Sewer 6/7/2021 Approved EUGENE CASSIDY
Special/Order Compliance 6/22/2021 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 7/8/2021 Approved EUGENE CASSIDY
Final 7/8/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/8/2021 Approved EUGENE CASSIDY
Green Building Final 7/8/2021 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 7/8/2021 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/8/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 7/8/2021 Approved EUGENE CASSIDY
Final 7/14/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 7/14/2021 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 7/14/2021 SGSOV Approved JOAQUIN GREENOUGH
Final 7/16/2021 OK to Issue CofO HORACE FULTZ
Green Building Final 7/16/2021 Approved HORACE FULTZ