11346 1/2 W TIARA ST 91601
Certificate Information: 11346 1/2 W TIARA ST 91601
- Application / Permit
- 20014-20000-01858
- Plan Check / Job No.
- B20VN06193
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD IRR. SHAPED 39'-11" x 26' TO AND CONVERT (E) 26'-5" x 20'-4" DET. GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- CofO Issued on 12/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/19/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 5/21/2020 | APPLICANT |
| Plan Check Approved | 1/13/2021 | ANGELICA MARTINEZ |
| Issued | 1/13/2021 | APPLICANT |
| CofO in Progress | 12/7/2021 | JOHN HAYES |
| CofO Issued | 12/28/2021 | MICHAEL SMITH |
| Permit Finaled | 12/28/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/3/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/3/2020 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 10/16/2020 | ISMAEL HERNANDEZ |
| Low Impact Development | Cleared | 12/3/2020 | SARAH YOUSSEF |
| Address approval | Cleared | 12/15/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/15/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/15/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Ideal Builders Group; Lic. No.: 944360-B | 15448 LEMAC STREET VAN NUYS, CA 91406 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/18/2021 | Conditional Approval | DANIEL ORRANTE |
| PLUMBING-Rough | 2/23/2021 | Partial Approval | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 3/3/2021 | Conditional Approval | DANIEL DREW |
| Footing/Foundation/Slab | 3/3/2021 | Conditional Approval | DANIEL DREW |
| BUILDING-Rough-Frame | 4/30/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 4/30/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2021 | Approved | DANIEL DREW |
| Gas Test | 4/30/2021 | Approved | DANIEL DREW |
| Green Building Rough | 4/30/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 4/30/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 4/30/2021 | Approved | DANIEL DREW |
| Wood Frame | 4/30/2021 | Not Ready for Inspection | DANIEL DREW |
| Insulation | 5/11/2021 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 5/11/2021 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 5/11/2021 | Approved | JOHN HAYES |
| Insulation | 5/12/2021 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 5/12/2021 | Off-Hour Fees Due | |
| Wood Frame | 5/12/2021 | Off-Hour Fees Due | |
| Insulation | 5/28/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Wood Frame | 5/28/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Insulation | 6/10/2021 | Approved | ALAN MORELOS |
| Drywall Nailing | 6/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 6/18/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/13/2021 | Approved | DANIEL DREW |
| Final | 8/13/2021 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 8/13/2021 | Approved | DANIEL DREW |
| Green Building Final | 8/13/2021 | Not Ready for Inspection | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 8/13/2021 | Approved | DANIEL DREW |
| Final | 11/30/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 11/30/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 12/7/2021 | Approved | JOHN HAYES |
| Final | 12/7/2021 | OK to Issue CofO | JOHN HAYES |
| HVAC-Final | 12/7/2021 | Approved | JOHN HAYES |
| PLUMBING-Final | 12/7/2021 | Approved | JOHN HAYES |
| Service/Power Release | 12/7/2021 | Approved | JOHN HAYES |
| Special/Order Compliance | 12/9/2021 | Approved | JOHN HAYES |