7911 N BEN AVE 91605
Certificate Information: 7911 N BEN AVE 91605
- Application / Permit
- 20014-20000-01836
- Plan Check / Job No.
- B20VN06142
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 15'7" X 27' IREREGULAR SHAPED ADDITION TO AND CONVERT THE (E) 24'11" X 20' RECREATION ROOM INTO A (N) ACCESSORY DWELLING , ALL WORK PER WFPP
- Permit Issued
- Issued on 8/14/2020
- Issuing Office
- Current Status
- CofO Issued on 3/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/12/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/14/2020 | RARES BODEA |
| Issued | 8/14/2020 | APPLICANT |
| CofO in Progress | 3/3/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 3/10/2022 | RONALD MYRICK |
| CofO Issued | 3/10/2022 | RONALD MYRICK |
| Permit Finaled | 3/10/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/13/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/13/2020 | ADRIAN CASTRO |
| ZI | Cleared | 5/13/2020 | HERMINIGILDO AGUSTIN |
| Construction within easement | Cleared | 7/29/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/11/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 9/30/2020 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 9/30/2020 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 10/13/2020 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 10/13/2020 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 11/9/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 11/9/2020 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 11/9/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 11/9/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/16/2020 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 11/16/2020 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 11/16/2020 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 11/16/2020 | Approved | JOHN HAYES |
| Drywall Nailing | 12/3/2020 | Approved | JOHN HAYES |
| Green Building Rough | 12/3/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/3/2020 | Partial Approval | JOHN HAYES |
| Shower Pan | 12/22/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/31/2020 | Approved | JOHN HAYES |
| Sewer | 1/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 1/28/2021 | Corrections Issued | JOHN HAYES |
| Sewer | 2/2/2021 | Approved | JOHN HAYES |
| Underground Mechanical | 2/2/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 6/4/2021 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 9/20/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 9/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 9/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 9/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 9/20/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 9/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 9/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/14/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 10/14/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 10/14/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 10/14/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 10/14/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 11/5/2021 | Not Ready for Inspection | DAVID MATSON |
| Service/Power Release | 11/5/2021 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 11/16/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 11/16/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 11/16/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 1/10/2022 | Corrections Issued | JOHN HAYES |
| Final | 1/20/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Final | 2/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 2/22/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 3/3/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |