14815 W GILMORE ST 91411
Certificate Information: 14815 W GILMORE ST 91411
- Application / Permit
- 20014-20000-01830
- Plan Check / Job No.
- B20VN06124
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSE (91SF) BEDROOM EXPANSION AT REAR UNIT WITH ATTACHED (383SF) RECREATION ROOM (WITH MAX 1/2 BATH) AT SECOND FLOOR OVER (474 SF) PARTIAL COVERED PARKING/PATIO TO (E) TWO STORY DUPLEX [SEE COMMENT].
- Permit Issued
- Issued on 12/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2020 | DAWN MC NULTY |
| Green Plans Picked Up | 5/29/2020 | APPLICANT |
| Corrections Issued | 6/9/2020 | DAWN MC NULTY |
| Quality Review Completed | 6/10/2020 | CHON CHIO KUO |
| Plan Check Approved | 12/3/2020 | DAWN MC NULTY |
| Issued | 12/16/2020 | APPLICANT |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| CofO in Progress | 1/25/2022 | RICHARD DOCKUS |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
| CofO Issued | 4/2/2022 | DEROLD HAUFF |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/24/2020 | MIGUEL GAMBOA |
| CPC | Cleared | 7/24/2020 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 7/24/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 11/4/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/12/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/30/2021 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Reinf. Concrete | 4/20/2021 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 4/27/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Reinf. Concrete | 5/3/2021 | Conditional Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/24/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 8/24/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/8/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 9/8/2021 | Approved | RICHARD DOCKUS |
| Wood Frame | 9/8/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/14/2021 | Approved | RICHARD DOCKUS |
| Insulation | 9/27/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/27/2021 | Approved | AMY COLIN |
| Drywall Nailing | 10/29/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 10/29/2021 | Approved | ALAN MORELOS |
| Green Building Final | 12/15/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 12/15/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 12/15/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 12/15/2021 | Approved | RICHARD DOCKUS |
| Final | 1/24/2022 | OK to Issue CofO | RICHARD DOCKUS |