14815 W GILMORE ST 91411

Certificate Information: 14815 W GILMORE ST 91411

Application / Permit
20014-20000-01830
Plan Check / Job No.
B20VN06124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSE (91SF) BEDROOM EXPANSION AT REAR UNIT WITH ATTACHED (383SF) RECREATION ROOM (WITH MAX 1/2 BATH) AT SECOND FLOOR OVER (474 SF) PARTIAL COVERED PARKING/PATIO TO (E) TWO STORY DUPLEX [SEE COMMENT].
Permit Issued
Issued on 12/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 DAWN MC NULTY
Green Plans Picked Up 5/29/2020 APPLICANT
Corrections Issued 6/9/2020 DAWN MC NULTY
Quality Review Completed 6/10/2020 CHON CHIO KUO
Plan Check Approved 12/3/2020 DAWN MC NULTY
Issued 12/16/2020 APPLICANT
Building Plans Picked Up 12/18/2020 APPLICANT
CofO in Progress 1/25/2022 RICHARD DOCKUS
Permit Finaled 4/2/2022 DEROLD HAUFF
CofO Issued 4/2/2022 DEROLD HAUFF
Permit Finaled 4/2/2022 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 7/24/2020 MIGUEL GAMBOA
CPC Cleared 7/24/2020 MIGUEL GAMBOA
Sewer availability Cleared 7/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/27/2020 ADRIAN CASTRO
Low Impact Development Cleared 11/4/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/12/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/30/2021 Partial Approval JENNIFER RABUCHIN
Deputy Reinf. Concrete 4/20/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 4/27/2021 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 5/3/2021 Conditional Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/24/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 8/24/2021 Approved RICHARD DOCKUS
ELECTRICAL-Rough 9/8/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 9/8/2021 Approved RICHARD DOCKUS
Wood Frame 9/8/2021 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 9/14/2021 Approved RICHARD DOCKUS
Insulation 9/27/2021 Approved AMY COLIN
Interior/Exterior Lathing 9/27/2021 Approved AMY COLIN
Drywall Nailing 10/29/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 10/29/2021 Approved ALAN MORELOS
Green Building Final 12/15/2021 Approved RICHARD DOCKUS
PLUMBING-Final 12/15/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 12/15/2021 Approved RICHARD DOCKUS
Final 1/24/2022 OK to Issue CofO RICHARD DOCKUS