6444-6446 N GEYSER AVE 91335

Certificate Information: 6444-6446 N GEYSER AVE 91335

Application / Permit
20014-20000-01817
Plan Check / Job No.
B20VN06090
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) CARPORT INTO GARAGE, ADD STORAGE ROOM & ACCESSORY DWELLING UNIT OVER GARAGE & STORAGE CREATING A 2-STORY SFD W/ ATTACHED GARAGE, STORAGE & ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
CofO Issued on 7/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 NILOOFAR MEHRAIN
Corrections Issued 5/28/2020 NILOOFAR MEHRAIN
Quality Review Completed 5/28/2020 STEVEN KIM
Building Plans Picked Up 6/1/2020 APPLICANT
Green Plans Picked Up 6/1/2020 APPLICANT
Applicant returned to address corrections 11/20/2020 NILOOFAR MEHRAIN
Plan Check Approved 1/14/2021 NILOOFAR MEHRAIN
Issued 2/9/2021 APPLICANT
CofO in Progress 6/14/2022 SEAN HAUPT
CofO Issued 7/21/2022 MICHAEL SMITH
Permit Finaled 7/21/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/1/2020 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 9/1/2020 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 9/1/2020 ABDULLAH SADOZAI
Sewer availability Cleared 9/9/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
Green Code Cleared 1/13/2021 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/8/2021 Partial Approval STEVEN BACK
Footing/Foundation/Slab 3/9/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 3/12/2021 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 3/12/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 3/16/2021 Partial Approval STEVEN BACK
Sewer 3/17/2021 Not Ready for Inspection STEVEN BACK
Deputy Drilled-In Anchors 3/22/2021 Partial Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 3/22/2021 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 3/22/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 3/22/2021 Corrections Issued STEVEN BACK
Sewer 3/22/2021 Approved STEVEN BACK
Excavation/Setback/Form/Re-Bar 3/23/2021 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 3/23/2021 Not Ready for Inspection STEVEN BACK
Gas Test 3/23/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 3/23/2021 Not Ready for Inspection STEVEN BACK
Pre-Inspection 3/23/2021 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 4/8/2021 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 4/8/2021 Conditional Approval STEVEN BACK
Deputy Wood Construction 4/22/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/22/2021 Partial Approval STEVEN BACK
Deputy Wood Construction 5/4/2021 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 5/27/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 5/27/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Corrections Issued STEVEN BACK
Green Building Rough 5/27/2021 Not Ready for Inspection STEVEN BACK
HVAC-Rough 5/27/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Approved STEVEN BACK
HVAC-Final 6/14/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Final 6/14/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 6/18/2021 Corrections Issued STEVEN BACK
HVAC-Rough 6/18/2021 Approved STEVEN BACK
PLUMBING-Rough 6/18/2021 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 6/25/2021 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 6/30/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 6/30/2021 Approved STEVEN BACK
Green Building Rough 6/30/2021 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 6/30/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 6/30/2021 Approved STEVEN BACK
Green Building Rough 7/7/2021 Not Ready for Inspection STEVEN BACK
Green Building Rough 7/14/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 8/6/2021 Corrections Issued STEVEN BACK
Green Building Rough 8/6/2021 Approved STEVEN BACK
Interior/Exterior Lathing 8/6/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 8/11/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 8/13/2021 Conditional Approval STEVEN BACK
Insulation 8/13/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 8/18/2021 No Access for Inspection STEVEN BACK
Drywall Nailing 8/18/2021 No Access for Inspection STEVEN BACK
BUILDING-Rough-Frame 8/20/2021 Approved STEVEN BACK
Drywall Nailing 8/20/2021 Approved STEVEN BACK
Insulation 8/20/2021 Approved STEVEN BACK
Final 11/30/2021 No Access for Inspection SEAN HAUPT
Footing/Foundation/Slab 11/30/2021 No Access for Inspection SEAN HAUPT
Green Building Final 11/30/2021 No Access for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 11/30/2021 No Access for Inspection SEAN HAUPT
Final 12/28/2021 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 12/28/2021 Approved SEAN HAUPT
Green Building Final 12/28/2021 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/28/2021 SGSOV Approved SEAN HAUPT
Smoke Detectors 12/28/2021 No Access for Inspection SEAN HAUPT
ELECTRICAL-Final 1/21/2022 Corrections Issued SEAN HAUPT
Final 1/21/2022 Corrections Issued SEAN HAUPT
Green Building Final 1/21/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 1/21/2022 Corrections Issued SEAN HAUPT
PLUMBING-Final 1/21/2022 Corrections Issued SEAN HAUPT
Smoke Detectors 1/21/2022 Corrections Issued SEAN HAUPT
ELECTRICAL-Final 6/13/2022 Approved SEAN HAUPT
Final 6/13/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 6/13/2022 Approved SEAN HAUPT
HVAC-Final 6/13/2022 Approved SEAN HAUPT
PLUMBING-Final 6/13/2022 Approved SEAN HAUPT
Service/Power Release 6/13/2022 Approved SEAN HAUPT
Smoke Detectors 6/13/2022 Approved SEAN HAUPT