717 N VISTA ST 90046
Certificate Information: 717 N VISTA ST 90046
- Application / Permit
- 20014-20000-01786
- Plan Check / Job No.
- B20VN06016
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) ONE STORY SINGLE FAMILY DWELLING AND INTERIOR REMODEL
- Permit Issued
- Issued on 12/8/2020
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | DANIEL YIP |
| Corrections Issued | 6/10/2020 | DANIEL YIP |
| Quality Review Completed | 6/30/2020 | QUAN NGHIEM |
| Plan Check Approved | 12/8/2020 | DANIEL YIP |
| Issued | 12/8/2020 | APPLICANT |
| CofO in Progress | 11/16/2021 | CHRIS CHRISTENSEN |
| No Progress | 12/22/2021 | CRAIG DAVIS |
| CofO in Progress | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 8/13/2020 | WALLIE JONG |
| Green Code | Cleared | 9/2/2020 | DANIEL YIP |
| Construction near power lines | Cleared | 12/1/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/21/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 12/21/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 12/21/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/6/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 1/6/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 1/6/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/21/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 1/21/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 2/9/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/16/2021 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/16/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/22/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/22/2021 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 2/23/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/23/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/19/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 3/25/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 4/13/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Sewer | 5/21/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 5/24/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/24/2021 | Approved | BENEVA JACKSON |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 8/9/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 8/9/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/9/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 9/9/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 9/13/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 9/17/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 9/17/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 9/17/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 10/22/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 10/22/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/2/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 11/2/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/15/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 11/15/2021 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 12/22/2021 | Corrections Issued | CRAIG DAVIS |