3729-3731 W LANDA ST 90039
Certificate Information: 3729-3731 W LANDA ST 90039
- Application / Permit
- 20014-20000-01758
- Plan Check / Job No.
- B20VN05944
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) CRAWL SPACE TO (N) 36'-6" X 13'-8" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) WITHIN (E) TWO STORY SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/16/2021
- Issuing Office
- Current Status
- CofO Issued on 3/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/20/2020 | SEWADA ZADOORIAN MILAGARDI |
| Green Plans Picked Up | 5/28/2020 | APPLICANT |
| Quality Review Completed | 6/4/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 6/15/2020 | APPLICANT |
| Plan Check Approved | 5/10/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 8/16/2021 | APPLICANT |
| CofO in Progress | 3/6/2025 | ENRIQUE MIRELES |
| Permit Finaled | 3/16/2025 | DEROLD HAUFF |
| CofO Issued | 3/16/2025 | DEROLD HAUFF |
| Permit Finaled | 3/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/22/2020 | CECILIO NAVARRO |
| Address approval | Cleared | 7/24/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 9/2/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/1/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 4/15/2021 | AARON COSTA |
Contact Information
| Contractor | Golden Age Construction Inc; Lic. No.: 1040171-B | 8265 SUNSET BLVD UNIT 205 WEST HOLLYWOOD, CA 90046 |
| Engineer | Andrada,, Aprile Larracas; Lic. No.: C81097 | 27356 DEARBORN DRIVE VALENCIA, CA 91354 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 10/1/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Pre-Inspection | 10/1/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/15/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/15/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 10/15/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/15/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/15/2021 | Approved | JOSEPH MCGARRY |
| Sewer | 10/15/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/22/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 10/22/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 11/1/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/1/2021 | Corrections Issued | JOSEPH MCGARRY |
| Shower Pan | 11/1/2021 | Corrections Issued | JOSEPH MCGARRY |
| Drywall Nailing | 11/5/2021 | Approved | JOSEPH MCGARRY |
| Gas Test | 11/5/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/5/2021 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 11/5/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/13/2022 | SGSOV Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/18/2022 | Approved | ARTHUR SARGSYAN |
| Final | 1/18/2022 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 1/18/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 1/18/2022 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 1/18/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/5/2025 | Approved | ENRIQUE MIRELES |
| Final | 3/5/2025 | OK to Issue CofO | ENRIQUE MIRELES |
| HVAC-Final | 3/5/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 3/5/2025 | Approved | ENRIQUE MIRELES |