4610 N CEDROS AVE 91403

Certificate Information: 4610 N CEDROS AVE 91403

Application / Permit
20014-20000-01755
Plan Check / Job No.
B20VN05931
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE SINGLE FAMILY DWELLING (20 LINEAR FEET ON NORTH SIDE OF BUILDING TO REMAIN); ADD NEW 82'-4" X 40' SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/1/2020
Issuing Office
Current Status
CofO Issued on 10/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 SELLA BENYAMIN
Corrections Issued 5/20/2020 SELLA BENYAMIN
Quality Review Completed 5/21/2020 STEVEN KIM
Building Plans Picked Up 5/22/2020 APPLICANT
Green Plans Picked Up 5/22/2020 APPLICANT
Plan Check Approved 9/29/2020 SELLA BENYAMIN
Issued 10/1/2020 APPLICANT
CofO in Progress 9/28/2021 ARAM AVEDISIAN
CofO Issued 10/15/2021 MICHAEL SMITH
Permit Finaled 10/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/15/2020 JOHN TRIANTAFYLLOS
Permit Cleared 6/15/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/15/2020 JOHN TRIANTAFYLLOS
Trees in Parkway Cleared 7/15/2020 JOHN KIM
Hydrant and Access approval Cleared 7/22/2020 KURT CORRAL
Low Impact Development Cleared 9/1/2020 ANDRES COVARRUBIAS
Green Code Cleared 9/10/2020 COLIN LOREDO
Roof/Waste drainage to street Cleared 9/10/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/8/2021 Partial Approval CHARLES POWELL
Underground Mechanical 1/8/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 1/14/2021 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 1/22/2021 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 2/26/2021 Approved CHARLES POWELL
Rough-Elec/Plmb/HVAC 3/10/2021 Approved CHARLES POWELL
Shower Pan 3/10/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 3/16/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 4/15/2021 Partial Approval CHARLES POWELL
Interior/Exterior Lathing 4/22/2021 Approved CHARLES POWELL
Insulation 4/29/2021 Corrections Issued ALAN MORELOS
Pre-Inspection 4/29/2021 Partial Inspection DEANDRE HOFFMAN
Green Building Rough 4/30/2021 Approved CHARLES POWELL
Insulation 4/30/2021 Approved CHARLES POWELL
Drywall Nailing 5/4/2021 Approved RYAN SALAZAR
Grounding or Bonding 7/16/2021 No Access for Inspection CHARLES POWELL
ELECTRICAL-Final 8/27/2021 Partial Approval CHARLES POWELL
Pre-Inspection 8/27/2021 Partial Inspection ALIZAH MAYAGOITIA
Service/Power Release 8/27/2021 Approved CHARLES POWELL
Final 9/9/2021 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 9/9/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 9/9/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/24/2021 Approved MISAEL ESPARZA
Final 9/24/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 9/24/2021 Approved MISAEL ESPARZA
MERV13>=Final 9/24/2021 Approved MISAEL ESPARZA
MERV13>=Rough 9/24/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 9/24/2021 Corrections Issued MISAEL ESPARZA
Final 9/27/2021 OK to Issue CofO ARAM AVEDISIAN
Smoke Detectors 9/27/2021 Approved ARAM AVEDISIAN