9711 N HELEN AVE 91040
Certificate Information: 9711 N HELEN AVE 91040
- Application / Permit
- 20014-20000-01747
- Plan Check / Job No.
- B20VN05913
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 13'-4" X 6'-3" ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING. (N) 18'-6" X 35'-9" PATIO COVER. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION & LA STANDARD PLAN. "COMPLY WITH DEPARTMENT ORDER effective date 12/20/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Current Status
- CofO Issued on 11/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | SERGIO MUNIZ |
| Corrections Issued | 6/3/2020 | SERGIO MUNIZ |
| Quality Review Completed | 6/19/2020 | STEVEN KIM |
| Green Plans Picked Up | 6/24/2020 | APPLICANT |
| Applicant returned to address corrections | 9/10/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 11/8/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/11/2022 | SERGIO MUNIZ |
| Plan Check Approved | 3/11/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Issued | 6/1/2022 | APPLICANT |
| CofO in Progress | 10/31/2023 | MARK VAN SLOOTEN |
| Permit Finaled | 11/8/2023 | DAVID JAMES |
| CofO Issued | 11/8/2023 | DAVID JAMES |
| Permit Finaled | 11/8/2023 | DAVID JAMES |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 7/10/2020 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 8/28/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 4/29/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Specific Plan | Cleared | 1/3/2022 | DANG NGUYEN |
| ZA Case | Cleared | 1/3/2022 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 1/21/2022 | ALEXANDER ANDREWS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/22/2022 | Approved | EMIL ALEXANDRIAN |
| Underground Mechanical | 9/22/2022 | Approved | EMIL ALEXANDRIAN |
| Rough-Elec/Plmb/HVAC | 10/13/2022 | Approved | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 10/27/2022 | Approved | EMIL ALEXANDRIAN |
| Green Building Rough | 10/27/2022 | Approved | EMIL ALEXANDRIAN |
| Drywall Nailing | 4/24/2023 | Approved | EMIL ALEXANDRIAN |
| Final | 4/24/2023 | Corrections Issued | EMIL ALEXANDRIAN |
| Footing/Foundation/Slab | 4/24/2023 | Approved | EMIL ALEXANDRIAN |
| Green Building Final | 4/24/2023 | Approved | EMIL ALEXANDRIAN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Not Ready | EMIL ALEXANDRIAN |
| Smoke Detectors | 4/24/2023 | Approved | EMIL ALEXANDRIAN |
| Final | 8/10/2023 | Conditional Approval | EMIL ALEXANDRIAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | EMIL ALEXANDRIAN |