20331 W PAYERAS ST 91311

Certificate Information: 20331 W PAYERAS ST 91311

Application / Permit
20014-20000-01745
Plan Check / Job No.
B20VN05910
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 16' X 20' ADDITION TO ENLARGE BEDROOM & NEW W.I.C. AND REMODEL BATHROOM & CONVERT BEDROOM TO STUDY ROOM OF (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/26/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2020 APPLICANT
Assigned to Plan Check Engineer 5/1/2020 RAPHAEL ROSAS
Corrections Issued 5/4/2020 RAPHAEL ROSAS
Plan Check Approved 5/12/2020 ROSENDO MEDINA
Issued 5/26/2020 LADBS
Building Plans Picked Up 5/29/2020 APPLICANT
CofO in Progress 9/16/2020 JEFFREY PARD
Permit Finaled 9/16/2020 JOHN JANSON
CofO Issued 9/16/2020 JOHN JANSON
Permit Finaled 9/16/2020 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 5/6/2020 ADRIAN CASTRO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Ing Construction & Inv; Lic. No.: 961589-B 5627 SEPULVEDA BOULEVARD # 208      VAN NUYS, CA 91411

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/12/2020 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 6/17/2020 Approved JEFFREY PARD
Underground Mechanical 6/17/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 7/6/2020 Corrections Issued JEFFREY PARD
HVAC-Rough 7/6/2020 Approved JEFFREY PARD
PLUMBING-Rough 7/6/2020 Approved JEFFREY PARD
Deputy Wood Construction 7/8/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 7/9/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 7/9/2020 Approved JEFFREY PARD
Green Building Rough 7/9/2020 Not Ready for Inspection JEFFREY PARD
Insulation 7/16/2020 Corrections Issued JEFFREY PARD
Insulation 7/23/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 7/23/2020 Approved JEFFREY PARD
Drywall Nailing 7/30/2020 Approved JEFFREY PARD
Shower Pan 7/30/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 9/4/2020 Approved JEFFREY PARD
Final 9/4/2020 Corrections Issued JEFFREY PARD
Green Building Final 9/4/2020 Approved JEFFREY PARD
Green Building Rough 9/4/2020 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 9/4/2020 SGSOV Approved JEFFREY PARD
Smoke Detectors 9/4/2020 Approved JEFFREY PARD
Final 9/15/2020 OK to Issue CofO JEFFREY PARD