5118 N LOUISE AVE 91316
Certificate Information: 5118 N LOUISE AVE 91316
- Application / Permit
- 20014-20000-01736
- Plan Check / Job No.
- B20VN05898
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 14'-0" X 26'-6" PATIO COVER TO AN (E) 2-STORY SFD PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2020 | JENNIFER LEE |
| Corrections Issued | 5/4/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 6/17/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 7/29/2020 | ROSENDO MEDINA |
| Issued | 8/17/2020 | APPLICANT |
| CofO in Progress | 5/14/2021 | STEVEN BACK |
| Permit Finaled | 5/19/2021 | MICHAEL SMITH |
| CofO Issued | 5/19/2021 | MICHAEL SMITH |
| Permit Finaled | 5/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/22/2020 | ADRIAN CASTRO |
| ZA Case | Cleared | 6/9/2020 | LAUREN PADICK |
| ZA Case | Cleared | 6/9/2020 | LAUREN PADICK |
| ZA Case | Cleared | 6/9/2020 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2020 | ADRIAN CASTRO |
Contact Information
| Architect | Silva,, Michael Dean; Lic. No.: C12976 | P O BOX 260192 ENCINO, CA 91426 |
| Contractor | Form Architectural; Lic. No.: 442000-B | 17721 VALLEY VISTA BLVD ENCINO, CA 91316 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/26/2020 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 10/27/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 10/27/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 10/30/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 12/2/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2020 | Approved | STEVEN BACK |
| Pre-Inspection | 12/2/2020 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 12/8/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 12/8/2020 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 12/31/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/20/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 1/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/11/2021 | SGSOV Not Ready | STEVEN BACK |
| Final | 5/14/2021 | OK to Issue CofO | STEVEN BACK |
| Pre-Inspection | 5/14/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/14/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 5/14/2021 | Approved | STEVEN BACK |