6438 W DAY ST 91042
Certificate Information: 6438 W DAY ST 91042
- Application / Permit
- 20014-20000-01735
- Plan Check / Job No.
- B20VN05897
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 35'-4" X 28'-8" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/9/2020
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2020 | JENNIFER LEE |
| Corrections Issued | 4/28/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 5/11/2020 | LUIS RINCON |
| Applicant returned to address corrections | 6/4/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 6/24/2020 | JEROME MAGAT PALMA |
| No Progress | 6/24/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 6/25/2020 | JEROME MAGAT PALMA |
| Issued | 7/9/2020 | APPLICANT |
| CofO in Progress | 6/9/2022 | MATTHEW NELSON |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 6/2/2020 | ANDRES COVARRUBIAS |
| GPI Written Notices | Cleared | 6/4/2020 | JENNIFER LEE |
| Grading Pre-Inspection | Cleared | 6/4/2020 | JENNIFER LEE |
| Roof/Waste drainage to street | Cleared | 6/19/2020 | JOHN LIN |
| Private sewage disp. approval | Cleared | 6/22/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C89006 | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/13/2020 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/24/2020 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 7/24/2020 | Partial Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 2/11/2021 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/19/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/19/2021 | Partial Approval | MATTHEW NELSON |
| Pre-Inspection | 3/19/2021 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/15/2021 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/15/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/15/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/15/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/27/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/27/2021 | Approved | MATTHEW NELSON |
| Insulation | 4/29/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/29/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 5/3/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 11/29/2021 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 1/14/2022 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 1/14/2022 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 1/14/2022 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 1/14/2022 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 1/14/2022 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 4/28/2022 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 5/3/2022 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 5/3/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/3/2022 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/8/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 6/8/2022 | Approved | MATTHEW NELSON |
| Final | 6/8/2022 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 6/8/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 6/8/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 6/8/2022 | Approved | MATTHEW NELSON |