8835 W SKYLINE DR 90046
Certificate Information: 8835 W SKYLINE DR 90046
- Application / Permit
- 20014-20000-01729
- Plan Check / Job No.
- B20VN05870
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 5' X 13'-9" TO EXTEND (E) KITCHEN, ADD IRREGULAR 34'-10" X 28'-4" FOR NEW BEDROOM AND REMODEL (E) BEDROOMS/BATHROOMS, ADD 17'-4" X 2'-0" AT FRONT TO EXTEND AND REMODEL (E) BEDROOMS/BATHROOMS; NEW SKYLIGHTS THROUGHOUT; REMODEL THROUGHOUT (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/1/2021
- Issuing Office
- Current Status
- CofO Issued on 3/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 4/29/2020 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 4/30/2020 | APPLICANT |
| Applicant returned to address corrections | 5/14/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 7/16/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/26/2020 | JEROME MAGAT PALMA |
| Issued | 6/1/2021 | APPLICANT |
| CofO in Progress | 3/13/2024 | RAUL BARAJAS |
| Permit Finaled | 3/14/2024 | RONALD MYRICK |
| CofO Issued | 3/14/2024 | RONALD MYRICK |
| Permit Finaled | 3/14/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 5/1/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 5/4/2020 | VASIL MIHALEV |
| Sewer availability | Cleared | 5/28/2020 | DINAH GARIN |
| Specific Plan | Cleared | 9/23/2020 | LIZZI BEDUYA |
Contact Information
| Architect | Getov,, Pavel Panayotov; Lic. No.: C32093 | 3565 REDWOOD AVENUE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/23/2021 | Corrections Issued | RAUL BARAJAS |
| Underground Mechanical | 6/23/2021 | Partial Approval | RAUL BARAJAS |
| Insulation | 9/15/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Interior/Exterior Lathing | 9/15/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Shower Pan | 9/15/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 11/19/2021 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 11/19/2021 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2021 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 11/19/2021 | Approved | RAUL BARAJAS |
| HVAC-Rough | 11/19/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 11/19/2021 | Approved | RAUL BARAJAS |
| Sewer | 11/19/2021 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/24/2021 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/10/2021 | Partial Approval | RAUL BARAJAS |
| Insulation | 9/6/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/6/2022 | Approved | RYAN SALAZAR |
| Shower Pan | 9/6/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/7/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 10/3/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 10/3/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 10/5/2023 | Approved | RAUL BARAJAS |
| Final | 10/11/2023 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 10/11/2023 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/5/2023 | Approved | RAUL BARAJAS |
| Final | 12/5/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 12/5/2023 | Approved | RAUL BARAJAS |
| HVAC-Final | 12/5/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 12/5/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/5/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/5/2023 | Approved | RAUL BARAJAS |
| Final | 3/8/2024 | Not Ready for Inspection | ROY SPAULDING |
| Final | 3/12/2024 | OK to Issue CofO | RAUL BARAJAS |