8134-8136 N NATICK AVE 91402
Certificate Information: 8134-8136 N NATICK AVE 91402
- Application / Permit
- 20014-20000-01726
- Plan Check / Job No.
- B20VN05869
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (N) 22' X 21' TWO STORY ATTACHED ACCESSORY DWELLING UNIT TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/22/2020 | SEWADA ZADOORIAN MILAGARDI |
| Green Plans Picked Up | 5/28/2020 | APPLICANT |
| Quality Review Completed | 6/1/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 6/5/2020 | APPLICANT |
| Plan Check Approved | 4/1/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/21/2021 | APPLICANT |
| CofO in Progress | 6/14/2022 | GREGG CUMMINGS |
| CofO Issued | 6/15/2022 | MICHAEL SMITH |
| Permit Finaled | 6/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 6/10/2020 | DAVID MATSON |
| Address approval | Cleared | 7/29/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 7/30/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 12/28/2020 | MITESH PATEL |
| Construction near power lines | Cleared | 2/2/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/2/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 3/1/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Santos,, Michael Fernandez; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/7/2021 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/11/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/11/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 5/11/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/17/2021 | Approved | DANIEL ORRANTE |
| Sewer | 5/17/2021 | Approved | DANIEL ORRANTE |
| Sewer | 5/24/2021 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 5/25/2021 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 5/28/2021 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/3/2021 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/3/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/14/2021 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 6/24/2021 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 6/28/2021 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 7/1/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Gas Test | 7/1/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/1/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 7/1/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 7/1/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 7/6/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/12/2021 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 7/12/2021 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 7/14/2021 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 7/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/20/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 9/20/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 9/20/2021 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/23/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/23/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/23/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 9/27/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 9/27/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 10/14/2021 | Conditional Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Rough | 10/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Wood Frame | 10/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/20/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 11/4/2021 | Approved | WILLIAM WREN |
| Shower Pan | 11/4/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 11/10/2021 | Approved | WILLIAM WREN |
| Green Building Rough | 11/10/2021 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/21/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/21/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 3/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/23/2022 | Conditional Approval | DAVID MATSON |
| Final | 5/23/2022 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 5/23/2022 | Corrections Issued | DAVID MATSON |
| BUILDING-Rough-Frame | 5/26/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 5/26/2022 | Corrections Issued | GREGG CUMMINGS |
| Smoke Detectors | 5/26/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/13/2022 | Approved | GREGG CUMMINGS |
| Final | 6/13/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 6/13/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 6/13/2022 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 6/13/2022 | Approved | GREGG CUMMINGS |