5632 N NORWICH AVE 91411
Certificate Information: 5632 N NORWICH AVE 91411
- Application / Permit
- 20014-20000-01721
- Plan Check / Job No.
- B20VN05862
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & MAJOR REMODEL TO (E) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 11/13/2020
- Issuing Office
- Current Status
- CofO Issued on 8/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/11/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 6/11/2020 | STEVEN KIM |
| Building Plans Picked Up | 6/11/2020 | APPLICANT |
| Green Plans Picked Up | 6/11/2020 | APPLICANT |
| Plan Check Approved | 10/27/2020 | NILOOFAR MEHRAIN |
| Issued | 11/13/2020 | APPLICANT |
| CofO in Progress | 12/8/2021 | RICHARD DOCKUS |
| Permit Finaled | 8/29/2022 | DANIEL ORRANTE |
| CofO Issued | 8/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 8/11/2020 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/11/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 8/25/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/23/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/24/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 10/27/2020 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Knudsen Mark Curtis; Lic. No.: 544786-B | 22639 MIRANDA ST WOODLAND HILLS, CA 91367 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/21/2020 | Partial Approval | JOHN HAYES |
| Green Building Rough | 12/21/2020 | Not Ready for Inspection | JOHN HAYES |
| Deputy Drilled-In Anchors | 2/18/2021 | Conditional Approval | MICHAEL TEMPLE |
| Deputy Wood Construction | 2/18/2021 | Conditional Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 3/1/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 3/1/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 3/8/2021 | Conditional Approval | DANIEL ORRANTE |
| ELECTRICAL-Rough | 3/22/2021 | Corrections Issued | MICHAEL TEMPLE |
| HVAC-Rough | 3/22/2021 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 3/22/2021 | Approved | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/1/2021 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/6/2021 | Partial Approval | DAVID MATSON |
| Drywall Nailing | 4/20/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Final | 11/3/2021 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 11/3/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 11/3/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 11/3/2021 | Approved | RICHARD DOCKUS |
| Final | 11/12/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 11/19/2021 | Conditional Approval | RICHARD DOCKUS |
| Final | 11/19/2021 | Corrections Issued | RICHARD DOCKUS |
| Final | 12/7/2021 | OK to Issue CofO | RICHARD DOCKUS |