5632 N NORWICH AVE 91411

Certificate Information: 5632 N NORWICH AVE 91411

Application / Permit
20014-20000-01721
Plan Check / Job No.
B20VN05862
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION & MAJOR REMODEL TO (E) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 11/13/2020
Issuing Office
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 NILOOFAR MEHRAIN
Corrections Issued 6/11/2020 NILOOFAR MEHRAIN
Quality Review Completed 6/11/2020 STEVEN KIM
Building Plans Picked Up 6/11/2020 APPLICANT
Green Plans Picked Up 6/11/2020 APPLICANT
Plan Check Approved 10/27/2020 NILOOFAR MEHRAIN
Issued 11/13/2020 APPLICANT
CofO in Progress 12/8/2021 RICHARD DOCKUS
Permit Finaled 8/29/2022 DANIEL ORRANTE
CofO Issued 8/29/2022 DANIEL ORRANTE
Permit Finaled 8/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 8/11/2020 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 8/11/2020 GABRIEL ROBLES
Sewer availability Cleared 8/11/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 8/25/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/23/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/24/2020 GABRIEL ROBLES
Green Code Cleared 10/27/2020 NILOOFAR MEHRAIN

Contact Information

Contractor Knudsen Mark Curtis; Lic. No.: 544786-B 22639 MIRANDA ST      WOODLAND HILLS, CA 91367
Engineer Wang,, Hongyu; Lic. No.: C72679 6270 MCLEOD DR STE 140      LAS VEGAS, NV 89120

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/19/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/21/2020 Partial Approval JOHN HAYES
Green Building Rough 12/21/2020 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 2/18/2021 Conditional Approval MICHAEL TEMPLE
Deputy Wood Construction 2/18/2021 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 3/1/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval JENNIFER RABUCHIN
Green Building Rough 3/1/2021 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 3/8/2021 Conditional Approval DANIEL ORRANTE
ELECTRICAL-Rough 3/22/2021 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 3/22/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 3/22/2021 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 4/1/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/1/2021 Approved JENNIFER RABUCHIN
Green Building Rough 4/1/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 4/1/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/1/2021 Partial Approval JENNIFER RABUCHIN
Shower Pan 4/1/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/6/2021 Partial Approval DAVID MATSON
Drywall Nailing 4/20/2021 Approved MARK JOHNSON
ELECTRICAL-Final 11/3/2021 Corrections Issued RICHARD DOCKUS
Green Building Final 11/3/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 11/3/2021 Approved RICHARD DOCKUS
Final 11/12/2021 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Final 11/19/2021 Conditional Approval RICHARD DOCKUS
Final 11/19/2021 Corrections Issued RICHARD DOCKUS
Final 12/7/2021 OK to Issue CofO RICHARD DOCKUS