5114 N BALBOA BLVD 91316

Certificate Information: 5114 N BALBOA BLVD 91316

Application / Permit
20014-20000-01720
Plan Check / Job No.
B20VN05860
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD ( 8'-9"x 13'-3") BATHROOM, LAUNDRY AND POWDER ROOM TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofO Issued on 7/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 TROY DEGUZMAN
Corrections Issued 5/20/2020 TROY DEGUZMAN
Building Plans Picked Up 6/1/2020 APPLICANT
Plan Check Approved 2/10/2021 TROY DEGUZMAN
Issued 2/10/2021 APPLICANT
CofO in Progress 7/3/2023 VINCENT HANLEY
Permit Finaled 7/27/2023 JOHN JANSON
CofO Issued 7/27/2023 JOHN JANSON
Permit Finaled 7/27/2023 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 7/27/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 7/28/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 10/22/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/12/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2021 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 3/25/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Corrections Issued DAVID SANDOVAL
HVAC-Rough 8/19/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 8/19/2021 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 8/25/2021 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 8/25/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Approved DAVID SANDOVAL
Green Building Rough 8/25/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 8/25/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 8/25/2021 Approved DAVID SANDOVAL
Insulation 9/15/2021 Approved RONALD COWAN
Interior/Exterior Lathing 9/15/2021 Approved RONALD COWAN
Shower Pan 9/15/2021 Approved RONALD COWAN
Drywall Nailing 9/27/2021 Approved RONALD COWAN
Green Building Rough 9/27/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 6/23/2023 Approved JOHN KIDWELL
Final 6/23/2023 Corrections Issued JOHN KIDWELL
Green Building Final 6/23/2023 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Approved JOHN KIDWELL
Smoke Detectors 6/23/2023 Approved JOHN KIDWELL
ELECTRICAL-Final 6/30/2023 Approved VINCENT HANLEY
Final 6/30/2023 OK to Issue CofO VINCENT HANLEY
Green Building Final 6/30/2023 Approved VINCENT HANLEY
HVAC-Final 6/30/2023 Approved VINCENT HANLEY
PLUMBING-Final 6/30/2023 Approved VINCENT HANLEY