12413 1/2 N TELFAIR AVE 91342
Certificate Information: 12413 1/2 N TELFAIR AVE 91342
- Application / Permit
- 20014-20000-01703
- Plan Check / Job No.
- B20VN05826
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- <2 OF 2> 14'11"X8'9" & 2'3"X6'3" ADDITIONS AND CONVERT THE (E) 14'11"X27'1" CHICKEN HOUSE INTO ADU
- Permit Issued
- Issued on 3/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | MARVEL DELACRUZ |
| Corrections Issued | 5/15/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 5/19/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/26/2020 | APPLICANT |
| Green Plans Picked Up | 7/8/2020 | APPLICANT |
| Applicant returned to address corrections | 1/4/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 2/23/2021 | MARVEL DELACRUZ |
| Issued | 3/15/2021 | APPLICANT |
| CofO in Progress | 11/28/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
| CofO Issued | 2/14/2024 | RUBEN SALAS |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 10/16/2020 | AARON COSTA |
| Low Impact Development | Cleared | 10/23/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/4/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/18/2020 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 1/4/2021 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 1/4/2021 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 11/9/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Sewer | 1/18/2022 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 1/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 1/31/2022 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 1/31/2022 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 2/24/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/2/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/19/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/25/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/29/2023 | Approved | JENNIFER RABUCHIN |
| Final | 11/29/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 11/29/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/29/2023 | Approved | JENNIFER RABUCHIN |