CONVERT PORTION OF (E) DET. 2-CAR GARAGE TO (N) ACCESSORY DWELLING UNIT TO MAKE A 1-CAR GARAGE, AND ADD 7'-8"x18' TO 1ST FLR, AND ADD A 22'-5"x14'-11 1/2" 2ND FLR TO (N) ADU PER LAMC 12.22 A.33 (c)-(d). [NO SUBMITTAL FEE, DEP. ERROR, FEE WAS CAPTURED UNDER 20014-20K-01699]
Permit Issued
Issued on 12/28/2020
Issuing Office
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 SEAN SHAHMIRI
Corrections Issued 5/12/2020 SEAN SHAHMIRI
Green Plans Picked Up 5/26/2020 APPLICANT
Quality Review Completed 6/8/2020 OMID HEDAYAT
Applicant returned to address corrections 10/23/2020 SEAN SHAHMIRI
Plan Check Approved 10/27/2020 SEAN SHAHMIRI
Applicant returned to address corrections 10/30/2020 SEAN SHAHMIRI
Issued 12/28/2020 APPLICANT
Building Plans Picked Up 1/6/2021 APPLICANT
CofO in Progress 7/6/2022 BRIAN SULLIVAN
Permit Finaled 8/26/2022 DEROLD HAUFF
CofO Issued 8/26/2022 DEROLD HAUFF
Permit Finaled 8/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/7/2020 MARTIN FRAGOSO
Green Code Cleared 9/15/2020 MICHAEL AYERS
Address approval Cleared 9/29/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 9/29/2020 ELAINE LEI
Roof/Waste drainage to street Cleared 9/29/2020 ELAINE LEI
Sewer availability Cleared 9/30/2020 ELAINE LEI
Construction within easement Cleared 10/6/2020 RIDWAN HARDY

Contact Information

Contractor Precision Remodeling; Lic. No.: 839615-B 2058 N MILLS AVE #633      CLAREMONT, CA 91711
Engineer Cox,, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/16/2021 Partial Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/16/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 4/16/2021 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 4/16/2021 Approved JOSEPH MCGARRY
METHANE-Subgrade 4/16/2021 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/13/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 5/13/2021 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 5/19/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/20/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 9/16/2021 Not Ready for Inspection BRIAN SULLIVAN
Gas Test 9/16/2021 Approved BRIAN SULLIVAN
HVAC-Rough 9/16/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 9/16/2021 Approved BRIAN SULLIVAN
Wood Frame 9/16/2021 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 12/21/2021 Not Ready for Inspection ARTHUR SARGSYAN
Rough-Elec/Plmb/HVAC 12/23/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 12/28/2021 Partial Approval JOSE AVILA
HVAC-Rough 12/28/2021 Not Ready for Inspection JOSE AVILA
Wood Frame 12/28/2021 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 1/4/2022 Approved BRIAN SULLIVAN
Green Building Rough 1/4/2022 Approved BRIAN SULLIVAN
Insulation 1/4/2022 Approved BRIAN SULLIVAN
METHANE-Rough 1/4/2022 Approved BRIAN SULLIVAN
Wood Frame 1/4/2022 Approved BRIAN SULLIVAN
Drywall Nailing 1/18/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 1/18/2022 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Final 6/1/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 6/1/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/1/2022 Approved ALIZAH MAYAGOITIA
Green Building Final 6/1/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 6/1/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 6/1/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/1/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 6/1/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/28/2022 Approved BRIAN SULLIVAN
Final 6/28/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 6/28/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 6/28/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 6/28/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 7/5/2022 Approved BRIAN SULLIVAN
Final 7/5/2022 OK to Issue CofO BRIAN SULLIVAN
HVAC-Final 7/5/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 7/5/2022 Approved BRIAN SULLIVAN