752 N MANSFIELD AVE 90038

Certificate Information: 752 N MANSFIELD AVE 90038

Application / Permit
20014-20000-01699
Plan Check / Job No.
B20VN05816
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
598 SF IRREGULAR ADDITION TO THE REAR AND 63 SF COVERED PORCH TO THE FRONT OF (E) SINGLE FAMILY DWELLING AND MAJOR REMODEL.
Permit Issued
Issued on 12/23/2020
Issuing Office
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 SEAN SHAHMIRI
Corrections Issued 5/12/2020 SEAN SHAHMIRI
Green Plans Picked Up 5/26/2020 APPLICANT
Quality Review Completed 6/8/2020 OMID HEDAYAT
Applicant returned to address corrections 10/23/2020 SEAN SHAHMIRI
Plan Check Approved 10/27/2020 SEAN SHAHMIRI
Applicant returned to address corrections 10/30/2020 SEAN SHAHMIRI
Issued 12/23/2020 APPLICANT
Building Plans Picked Up 1/6/2021 APPLICANT
CofO in Progress 7/6/2022 BRIAN SULLIVAN
Permit Finaled 8/26/2022 DEROLD HAUFF
CofO Issued 8/26/2022 DEROLD HAUFF
Permit Finaled 8/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/7/2020 MARTIN FRAGOSO
Green Code Cleared 9/15/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 9/29/2020 ELAINE LEI
Sewer availability Cleared 9/29/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/23/2020 ELAINE LEI

Contact Information

Contractor Precision Remodeling; Lic. No.: 839615-B 2058 N MILLS AVE #633      CLAREMONT, CA 91711
Engineer Cox,, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/30/2020 Corrections Issued RAUL BARAJAS
METHANE-Barrier 12/30/2020 Not Ready for Inspection RAUL BARAJAS
METHANE-Subgrade 12/30/2020 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 1/6/2021 Approved BRIAN SULLIVAN
METHANE-Barrier 1/6/2021 Approved BRIAN SULLIVAN
METHANE-Subgrade 1/6/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 9/28/2021 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/28/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 9/28/2021 Approved CHRIS CHRISTENSEN
Insulation 9/28/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/6/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 10/6/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 6/1/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/1/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 6/1/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 6/1/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 6/1/2022 Approved ALIZAH MAYAGOITIA
METHANE-Final 6/1/2022 Approved ALIZAH MAYAGOITIA
METHANE-Rough 6/1/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 6/1/2022 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/1/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 6/1/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/28/2022 Approved BRIAN SULLIVAN
Final 6/28/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 6/28/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 6/28/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Approved BRIAN SULLIVAN
ELECTRICAL-Final 7/5/2022 Approved BRIAN SULLIVAN
Final 7/5/2022 OK to Issue CofO BRIAN SULLIVAN
HVAC-Final 7/5/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 7/5/2022 Approved BRIAN SULLIVAN