752 N MANSFIELD AVE 90038
Certificate Information: 752 N MANSFIELD AVE 90038
- Application / Permit
- 20014-20000-01699
- Plan Check / Job No.
- B20VN05816
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 598 SF IRREGULAR ADDITION TO THE REAR AND 63 SF COVERED PORCH TO THE FRONT OF (E) SINGLE FAMILY DWELLING AND MAJOR REMODEL.
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 8/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | SEAN SHAHMIRI |
| Corrections Issued | 5/12/2020 | SEAN SHAHMIRI |
| Green Plans Picked Up | 5/26/2020 | APPLICANT |
| Quality Review Completed | 6/8/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/23/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 10/27/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 10/30/2020 | SEAN SHAHMIRI |
| Issued | 12/23/2020 | APPLICANT |
| Building Plans Picked Up | 1/6/2021 | APPLICANT |
| CofO in Progress | 7/6/2022 | BRIAN SULLIVAN |
| Permit Finaled | 8/26/2022 | DEROLD HAUFF |
| CofO Issued | 8/26/2022 | DEROLD HAUFF |
| Permit Finaled | 8/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/7/2020 | MARTIN FRAGOSO |
| Green Code | Cleared | 9/15/2020 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 9/29/2020 | ELAINE LEI |
| Sewer availability | Cleared | 9/29/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | ELAINE LEI |
Contact Information
| Contractor | Precision Remodeling; Lic. No.: 839615-B | 2058 N MILLS AVE #633 CLAREMONT, CA 91711 |
| Engineer | Cox,, Steven Jeffrey; Lic. No.: C48940 | 130 MAGELLAN ST THOUSAND OAKS, CA 91360 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/30/2020 | Corrections Issued | RAUL BARAJAS |
| METHANE-Barrier | 12/30/2020 | Not Ready for Inspection | RAUL BARAJAS |
| METHANE-Subgrade | 12/30/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/6/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Barrier | 1/6/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 1/6/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/28/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/28/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/28/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 9/28/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/6/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 10/6/2021 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/1/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/1/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 6/1/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/1/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/1/2022 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Final | 6/1/2022 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 6/1/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/1/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/1/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/1/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/28/2022 | Approved | BRIAN SULLIVAN |
| Final | 6/28/2022 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 6/28/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 6/28/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/28/2022 | SGSOV Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 7/5/2022 | Approved | BRIAN SULLIVAN |
| Final | 7/5/2022 | OK to Issue CofO | BRIAN SULLIVAN |
| HVAC-Final | 7/5/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 7/5/2022 | Approved | BRIAN SULLIVAN |