6934 N ETIWANDA AVE 91335

Certificate Information: 6934 N ETIWANDA AVE 91335

Application / Permit
20014-20000-01692
Plan Check / Job No.
B20VN05802
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ECPC: 132 SQ. FT. ADDITION TO AND CONVERT THE (E) 367 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/20/2020
Issuing Office
Current Status
CofO Issued on 10/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 4/27/2020 PARISA ZAHABI
Corrections Issued 4/27/2020 PARISA ZAHABI
Building Plans Picked Up 4/30/2020 APPLICANT
Applicant returned to address corrections 5/7/2020 JEFFREY TANGONAN
Plan Check Approved 5/19/2020 THOMAS SHERMAN
Issued 5/20/2020 APPLICANT
CofO in Progress 10/8/2020 VINCENT HANLEY
Permit Finaled 10/19/2020 MICHAEL SMITH
CofO Issued 10/19/2020 MICHAEL SMITH
Permit Finaled 10/19/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/12/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/12/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 5/12/2020 GUILLERMO PETRA
Sewer availability Cleared 5/12/2020 GUILLERMO PETRA
ZI Cleared 5/13/2020 LAUREN PADICK

Contact Information

Engineer Nguyen,, Quynh Anh; Lic. No.: C58592 12000 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/25/2020 Approved VINCENT HANLEY
PLUMBING-Rough 6/25/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 7/8/2020 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 7/8/2020 Corrections Issued STEVEN BACK
Green Building Rough 7/8/2020 Not Ready for Inspection STEVEN BACK
HVAC-Rough 7/8/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 7/8/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 7/15/2020 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 7/15/2020 Partial Approval VINCENT HANLEY
Green Building Rough 7/15/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 7/15/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 7/16/2020 Partial Approval VINCENT HANLEY
Insulation 7/22/2020 Approved VINCENT HANLEY
Drywall Nailing 7/28/2020 Approved VINCENT HANLEY
Green Building Rough 7/28/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/12/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/11/2020 Approved VINCENT HANLEY
Final 9/11/2020 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/11/2020 SGSOV Not Ready VINCENT HANLEY
Sewer 9/11/2020 Approved VINCENT HANLEY
Smoke Detectors 9/11/2020 Not Ready for Inspection VINCENT HANLEY
Final 9/21/2020 Corrections Issued VINCENT HANLEY
Green Building Final 9/21/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/21/2020 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 9/21/2020 Approved VINCENT HANLEY
Final 9/30/2020 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/30/2020 SGSOV Approved VINCENT HANLEY
Final 10/6/2020 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 10/8/2020 Approved VINCENT HANLEY
Final 10/8/2020 OK to Issue CofO VINCENT HANLEY
HVAC-Final 10/8/2020 Approved VINCENT HANLEY
PLUMBING-Final 10/8/2020 Approved VINCENT HANLEY